PROGRESS OF WORKS FOR THE MONTH OF
FEB.2018

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG/FM

2017-18

Exp. Up tothe month/ Cum. Exp.

Physical progress

NLPB-6

Rayadurga-Tumkur(207Km)(12 Block sections)

2007-08

1714.49

on 50:50 cost sharing basis betweenRly and Gok / GoAP

556.76

81.00/ 1.20

 

96.70/ 653.46

25%

Remarks:-

 

Section from Rayadurga-Kalyanadurga-Kadiridevarapalli (63 km) which falls in A.P. was commissioned in 2016-17. In the recent past about 266 Acres of land has been handed over by GoK to Railway over a length of 23 km from Tumkuru end. Earthwork and Bridge work has commenced in this stretch in Aug. 2017. For the balance land of 947 Ac, SIA study has  been completed.  Preliminary notification is under issued under new L.A.Act by GoK.
 


 




Source : South Western Railway CMS Team Last Reviewed on: 13-03-2018