PROGRESS OF WORKSFOR THEMONTH OF
OCT.2017

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG/RE

2017-18

Exp. Up tothe month/ Cum. Exp.

Physical progress

NLPB-6

Rayadurga-Tumkur(207Km)(12 Block sections)

2007-08

1714.49

on 50:50 cost sharing basis betweenRly and Gok / GoAP

556.76

81.00/ 61.00

 

56.60/  613.36

25%

Remarks:-

 

Section from Rayadurga-Kalyanadurga-Kadiridevarapalli (63 km) which falls in A.P. was commissioned in 2016-17. The work could not start in Karnataka State due to non-handing over of land by GoK.In the recent past about 266 Acres of land has been handed over by GoK to Railway over a length of 23 km from Tumkuru end.Earthwork and Bridge work has commenced in this stretch in Aug. 2017. 
 


 




Source : South Western Railway CMS Team Last Reviewed on: 13-11-2017  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.