PROGRESS OF WORKS FOR THE MONTH OF
SEP.2017



Cate-gory

Details of Work

Year of sanc-tion

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG

2017-18

Exp. Up tothe month/ Cum. Exp.

Physical progress

NLPB-2

Kadur-Chikmagalur-Sakleshpur

(93kms)

1996-97

889.52

On 50:50 cost sharing basis to Kadur-Chikmagalur (42 km) & Chikmagalur – Sakleshpurland free of cost balance cost on 50:50 basis between Gok & Rly.

421.69

20.00

 

2.88/ 424.57

49%

Remarks:-

 

ØSection from Kadur to Chikmagalur (46 km) was completed and commissioned on 19.11.2013.

ØPhase II works between Chikmagalur – Sakleshpur were frozen by Railway Board since 2007 and defreezed during 2013.

ØWork in Chikmagalur – Sakleshpur section (47 km) could not be started as the balance land totalling 885 acres is yet to be handed over by GoK.  

Target  for balance section:  Chikmagalur-Saklelshpur (47 km) can be completed by 2018, subject to acquisition of land by GoK.  

 




Source : South Western Railway CMS Team Last Reviewed on: 04-10-2017  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.