PROGRESS OF WORKS FOR THE MONTH OF
FEB.2018



Cate-gory

Details of Work

Year of sanc-tion

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG/RE

2017-18

Exp. Up tothe month/ Cum. Exp.

Physical progress

NLPB-2

Kadur-Chikmagalur-Sakleshpur

(93kms)

1996-97

889.52

On 50:50 cost sharing basis to Kadur-Chikmagalur (42 km) & Chikmagalur – Sakleshpurland free of cost balance cost on 50:50 basis between Gok & Rly.

421.69

20.00/ 6.10

 

6.51/ 428.21

49%

Remarks:-

 

ØSection from Kadur to Chikmagalur (46 km) was completed and commissioned on 19.11.2013.

ØPhase II works between Chikmagalur – Sakleshpur were frozen by Railway Board since 2007 and defreezed during 2013.

ØWork in Chikmagalur – Sakleshpur section (47 km) could not be started as the balance land totalling 885 acres is yet to be handed over by GoK.  


 