Sl. No

Cate-gory

Details of Work

Year of sanction

Original sanctioned Pink Book cost

Latest Anticipated /Sanctioned Cost

Cum.Exp. Up to  31.03.2016

Physical progress

4.

NL   PB-2

Kadur-Chikmagalur-Sakleshpur       

(93kms)

1996-97

157.00

889.52

(Kadur-Chikmagalur (46 km) on 50:50 cost sharing basis for & Chikmagalur – Sakleshpur (47 km) with  land free of cost in addition to 50:50 cost sharing between Gok & Rly.)

406.52

49%

 
  ØSection from Kadur to Chikmagalur (46 km) was completed and commissioned on 19.11.2013.

ØPhase II works between Chikmagalur – Sakleshpur were frozen by Railway Board since 2007 and defreezed during 2013.  

ØWork in Chikmagalur – Sakleshpur section (47 km) could not be  started  as the balance land totalling 885 acres is yet to be handed over by GoK.  


Target  for balance section:  Chikmagalur-Saklelshpur (47 km) can be completed by 2018, subject to acquisition                                            of land by GoK and adequate allotment of funds.  




Source : South Western Railway CMS Team Last Reviewed on: 15-04-2016  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.