PROGRESS OF WORKSFOR THEMONTH OF
SEP.2017


Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG

2017-18

Exp. Up tothe month/ Cum. Exp.

Physical progress

NL PB-5

Hejjala-Chamarajanagar (142 km)

(part of Bangalore-Satyamangalam(260 kms)

1996-97

1382.78

on 50:50 cost sharing basis & land free of cost by GOKfor Hejjala to Chamarajanagar

5.59

1.00

0.53/

6.12

Nil

Remarks:-

 

Originally the project was sanctioned between Bangalore-Satyamangalam (260 km). Permission was not granted by Tamilnadu Government as well as CEC to carry out survey in the Satyamangalam Forest Area.Hence project is now being taken up from Hejjala to Chamarajnagar (142 Kms).Land yet tobe given by State Govt.




Source : South Western Railway CMS Team Last Reviewed on: 04-10-2017  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.