PROGRESS OF WORKS FOR THE MONTH OF
FEB.2018


Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG/FM

2017-18

Exp. Up tothe month/ Cum. Exp.

Physical progress

NL PB-5

Hejjala-Chamarajanagar (142 km)

(part of Bangalore-Satyamangalam(260 kms)

1996-97

1382.78

on 50:50 cost sharing basis & land free of cost by GOKfor Hejjala to Chamarajanagar

5.59

1.00/ 0.54

0.53/

6.12

Nil

Remarks:-

 

Originally the project was sanctioned between Bangalore-Satyamangalam (260 km). Permission was not granted by Tamilnadu Government as well as CEC to carry out survey in the Satyamangalam Forest Area.Hence project is now being taken up from Hejjala to Chamarajnagar (142 Kms).Land yet to be given by State Govt.




Source : South Western Railway CMS Team Last Reviewed on: 13-03-2018