PROGRESS OF WORKS FOR THE MONTH OF
FEB.2018

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG/ FM 2017-18

Exp. Up tothe month/ Cum. exp

Physical progress

NL

PB-11

Marikuppam – Kuppam

( 23.70 Km)

2012-13

279.54

1.51

15.00/  3.00

2.24/ 

 3.95

Nil

Remarks

 

Work could not be commenced till date due to non- availability of land.

 





Source : South Western Railway CMS Team Last Reviewed on: 13-03-2018