Sl. No

Cate-gory

Details of Work

Year of sanction

Original sanctioned Pink Book cost

Latest Anticipated /Sanctioned Cost

Cum.Exp. Up to  31.03.16

Physical progress

16

NL  PB-7

Bagalkot-Kudachi     (142 kms)

2010-11

816.14

986.30

(on 50:50 cost sharing basis & land free of cost by GOK)

209.06

7%

 

Ø 551 acres of land from Bagalkot end has been acquired out of 2279 acres of land required  for the whole project

Ø No land has been handed over from Kudachi side (Belgaum district).

Ø Engine rolling for 10 km. length from Bagalkot end was done on 30.03.2014. Further work is in progress  in 20 kms stretch for which land is available.

The section between Bagalkot-Khajdoni (30 km) is targeted for commissioning on “One Train Only System” by May 2017.


 Target:- Project can be completed in 4-5 years by subject to handing over of balance land of 1729 acres by GoK and allotment of adequate fund 





Source : South Western Railway CMS Team Last Reviewed on: 13-04-2017  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.