Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG 2017-18

Exp. Up to the month/ Cum. exp

Physical progress

DLPB-33

Shivani-Hosadurga (10 kms)

2011-12

*49.36

62.48

2.00

0.03/62.51

100%

Remarks:-

Project has been completed and commissioned.