Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG 2017-18

Exp. Up to the month/ Cum. exp

Physical progress

DLPB-32

Hospet -Hubli-Londa-Vasco-da-gama(352.58 Km)

2010-11

928.85

693.32

434.70

131.08/ 814.46

70%

Remarks:-This project is being executed by RVNL. So far 67 km. has been commissioned. Further 36 km is targetted for commissioning in 2017-18.




Source : South Western Railway CMS Team Last Reviewed on: 13-03-2018