Sl. No

Cate-gory

Details of Work

Year of sanction

Original sanctioned Pink Book cost

Latest Anticipated /Sanctioned Cost

Cum.Exp. Up to  31.03.17

Physical progress

10

DL

PB-34

Hotgi-Kudgi-Gadag (284 km)

2014-15

1618.00

1618.00

147.92

164.63 (NTPC)

30%

 

ØThe doubling project has been sanctioned by Railway Board in 2014-15. Clearance from CCEA is received on 01.10.2015.  

ØAn amount of Rs. 946 Cr. has been deposited by M/s NTPC towards part of the project (Hotgi-Kudgi)  under Customer Funding Model.

ØDetailed Estimate has been sanctioned on 13.10.15

   New Crossing station @ Kudgi with 4 lines for giving connectivity to NTPC was commissioned on 29.01.2017.

  1. The project is planned for completion by 2020-21.However, as per agreement with NTPC for Customer Funding, the section between Kudgi-Hotgi shall be completed by 2019-20.




Source : South Western Railway CMS Team Last Reviewed on: 13-04-2017  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.