Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG 2017-18

Exp. Up tothe month/ Cum. exp

Physical progress

DL

PB-35

Hotgi-Kudgi-Gadag (284 km)

2014-15

1614.59

147.92

170.89 (NTPC)

140.00

204.00

(NTPC)

112.68/259.84   124.49/295.39

(NTPC)

30%

Remarks:-

Doubling for part length of this project, i.e. from Hotgi-Kudgi (134 km) is taken up under Customer Funding Model.For this purpose NTPC have deposited Rs.946 cr. with Railway.

New Crossing station @ Kudgi with 4 lines for giving connectivity to NTPC was commissioned on 29.01.2017.   Phase I of Indi Road commissioned on 28.07.17.  Tadwal Yard commissioned as 4 line station on 02.09.2017.

Work is in progress in the section between Minchinal-Lachyan (42.5 km) is targeted for commissioning during 2017-18.

 




Source : South Western Railway CMS Team Last Reviewed on: 13-03-2018