Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG / FM 2017-18

Exp. Up tothe month/ Cum. exp

Physical progress

DL

PB-36

 

Yelahanka-Penukonda

(120.55 km)

2015-16

860.43

213.40

120.00 / 131.88

144.28/ 357.68

Nil

Remarks:-

1. A portion of this project, i.e. 48.2 km falls in A.P. out of total length of 120.53 km.

2. Work is in progress in the section between Makalidurga-Devarapalli (36 km).  Earthwork and bridge work has been completed and linking is in progress.




Source : South Western Railway CMS Team Last Reviewed on: 13-03-2018