Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG / FM 2017-18

Exp. Up tothe month/ Cum. exp

Physical progress

DL

PB-38

Arsikere-Tumkur(96 km)

2015-16

578.00

239.59

140.00 / 109.71

102.09/ 341.68

24%

Remarks:-

 

Work is in progress in the section between Arsikere-Karadi (36 km).  In this stretch, earthwork in formation and minor bridges, major bridges have been completed.  Track linking is in progress.




Source : South Western Railway CMS Team Last Reviewed on: 13-03-2018