Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG/ FM 2017-18

Exp. Up tothe month/ Cum. exp

Physical progress

DL

PB-37

Hubli-Chikjajur (190 km)

2015-16

1140.93

311.74

200.00/ 206.00

209.72/ 521.44

Nil

Remarks :-

Work is in progress in the section between Chikjajur-Tolahunse (37 km).  Earthwork, minor and major bridge works have been completed and track linking is in progress.

 




Source : South Western Railway CMS Team Last Reviewed on: 13-03-2018