Targets for 2025-26


Targets for 2025-26


Targets for Commissioning of Doubling & New Lines for 2025-26

SN

Name of the project (km)

Section Targeted

CE Incharge

Length (Km)

Doubling Projects

1

Penukonda - Dharmavaram (42)

Makkajapalli - Nagasamudram

CE/II/BNC

15

2

Nagasamudram - Dharmavaram

15

3

Hotgi-Kudgi-Gadag (284)

Bagalkot - Mugalolli

CE/I/UBL

7.9

4

Jadramakunte - Almatti

14.9

5

Almatti – Wandal

9.6

6

Baiyyappanahalli - Hosur
(48)

Bellandur - Karmelaram

K RIDE

3.5

7

Anekal - Maranayakanahalli

6.9

8

Baiyyapanahalli - Bellandur

9.7

9

Maranayakanahalli-Hosur

7.6

11

Yeshwantpur - Channsandra
(25)

Yeswanthpur - Yeswanthpur byepass & Lottegollahalli - Hebbal

10.4

12

Byappanahalli A cabin - Channasandra
(executed by CN/SWR)

CE/II/BNC

2.7

13

Bangalore Cantonment - Whitefield Quadrupling (38)

Baiyyappanahalli Cantonment - Baiyyappanahalli West cabin

CPM/GSU/
SBC

13.4

14

Baiyyappanahalli - Whitefield

24.6

Total Doubling

141.2

New Line Projects

12

Tumkur - Rayadurga (206 Km)

Tumkur - Urukere

CE/I/BNC

11.1

13

Tumkur - Chitradurg - Davangere (191 Km)

Urukere - Thimmarajanahalli

CE/III/BNC

13.3

17

Tumkur - Rayadurga
(206 Km)

Pavagada - Doddahalli

CE/I/BNC

16

18

Tumkur - Chitradurg - Davangere (191 Km)

Hebbalu - Tolahunse

CE/III/BNC

15.51

19

Marikuppam-Kuppam New line (23.7km)

Marikuppam - Virupakshapura

CE/II/BNC

4.3

20

Bagalkot - Kudachi (142 Km)

Lokapur - Dadanahatti

CE/I/UBL

6.6

Total Doubling

66.81

Grand Total

208.01

 

Source : South Western Railway Last Reviewed : 15-06-2026