SN

Type of work
( CS/AW )

Description of work ( LC No., between stations & section)

Month & year of commission

2013-14

1

CS

ROB in lieu of LC no. 40 & 41 between Tumakuru- Mallasandra stations in Tumakuru-Arsikere section

Apr-13

2014-15

1

CS

ROB in lieu of LC no. 33 between Bhadravati-Sivamogga stations in Birur-Talaguppa section

Apr-14

2

CS

RUB in lieu of LC No. 4 between Nayandahalli to (RPC layout) in Bangalore -Mysore

Jan-15

3

AW

RUB in Lieu of LC No.52 between Channapatna-settihalli stations in Ramanagaram-Mysuru section.

May-14

4

AW

RUB in lieu of LC 58 between Settihalli-Maddur stations in Ramanagaram-Mysuru section.

May-14

5

AW

RUB in lieu of LC No 140 between Ajjampura-Shivani stations in Birur-Chikjajur section

Dec-14

6

AW

RUB in lieu of LC No 149 between Shivani-Hosadurga Road stations in Birur-Chikjajur section.

Mar-15

7

AW

Subway in lieu of LC NO. 157 between Ramagiri-Holakere stations in Birur-Chikjajur section

Mar-15

8

AW

Subway in lieu of LC NO. 158 between Ramagiri-Holakere stations in Birur-Chikjajur section

Mar-15

9

AW

Subway in lieu of LC NO. 163 between Ramagiri-Holakere stations in Birur-Chikjajur section

Mar-15

10

AW

Subway in lieu of LC NO. 165 between Ramagiri-Holakere stations in Birur-Chikjajur section.

Mar-15

11

AW

Subway in lieu of LC NO. 166 between Ramagiri-Holakere stations in Birur-Chikjajur section.

Mar-15

12

AW

Subway in lieu of LC NO. 167 between Chikjajur-Sasalu stations in Birur-Chikjajur section.

Mar-15

2015-16

1

CS

ROB in lieu of LC no. 11 between Yeshvantpur -Yelahanka stations in Yeshvantpur -Yelahanka section

Jan-16

2

CS

ROB in lieu of LC No:198 between Davanagere-Tolahunse stations in Chikjajur-Hubballi section.

Jan-16

3

CS

RUB in lieu of LC No.64 between Koppal – Ginigera stations in Hosapete-Hubballi section

Mar-16

4

CS

RUB at LC No. 10 A between YPR and YNK stations in Yesvantpur -Yelahanka section

Mar-16

5

CS

ROB in lieu of LC No. 95 A between Pandavapaura- Byadarahalli stations in Bengaluru-Mysuru section.

Nov-15

6

CS

RUB in lieu of LC No 101 between Srirangapattana - Naganahally stations in Bengaluru-Mysuru section.

Nov-15

7

AW

LHS in lieu of LC No 145 at Km 239/200-300 between Shivani-Hosadurga road stations . in Arsikere Harihar section

Aug-15

8

Deposit

RUB in lieu of LC no:40 between Tumakuru-Mallasandra stations.(deposit work for TUDA of GOK) in Tumakuru- arsikere section.

Mar-16

9

Deposit

ROB in lieu of LC No. 113 between nagasamudram and Dharavaram stations in Baiyyappanahalli-Dharmavaram section

Feb-16

2016-17

1

CS

ROB in lieu of LC no. 4 & 4-B near Jalahalli between Yesvantpur-chikbanavara stations in Bengalru- Tumakuru section. (LC no.4)

Jan-17

2

CS

ROB in lieu of LC no. 4 & 4-B near Jalahalli between Yesvantpur-chikbanavara stations in Bengalru- Tumakuru section. (LC no. 4- B)

Jan-17

3

CS

ROB in lieu of LC no. 114 Between Bellari-Bellari cantonemnent stations in Hosapete-Ballari section.

Feb-17

4

CS

ROB in lieu of LC No.385 at Belgavi station between Belagavi -Sambre stations in Londa-Miraj section

Oct-16

5

AW

ROB in lieu of LCNo. 156 between Hosadurga road -Ramagiri stations in Arsikere-Chikjajuru section

Sep-16

6

AW

ROB in lieuof LC No. 169 between Chikjajur-Sasalu stations in Chikjajur-Hubballi section.

Oct-16

7

AW

RUB in lieu of LC No.168 between Chikjajur-Sasalu stations in Chikjajur-Hubballi section.

Sep-16

8

CS

ROB in lieu of LC No:131 between Baiiyyappanahalli-Carmelram in YPR-Salem section

Mar-17

2017-18

1

CS

ROB in lieu of LC No.388-A. at Belgavi station between Belagavi -Sambre stations in Londa-Miraj section

Mar-18

2

CS

ROB in lieu of LC No.32 between Doddaballapur - Oddarahalli stations in Baiyyappanahalli-Dharmavaram section.

Jan-18

3

CS

ROB in lieu of LC No.112 between Bellari Cant- Bellari Junction stations in Hosapete-Bellari section.

Nov-17

4

CS

ROB in lieu of LC No.1 between Hubballi - Kusugal stations in Hubballi- Hosapete section.

Sep-17

5

CS

ROB in lieu of LC no:4-A with subway between Yesvantpur- Yelahanka stations between Yesvantpur-Yelahanka section

Jun-17

6

CS

ROB in lieu of LC No:21 between Yelahanka-Rajankunti stations in Baiyyappanahalli-Dharmavaram section.

Aug-17

7

AW

ROB in lieu of LCNo. 176 between Mayakonda-Sasalu stations Chickjajur-Hubli section.

Feb-18

8

AW

ROB in lieu of LCNo. 213 at Chalgeri yard between Ranebennur-Chalgeri stations in Chickjajur-Hubli section.

Feb-18

2018-19

1

CS

ROB in lieu of LC No.27 between Rajanukunti-Doddaballapura stations in Baiyyappanahalli-Dharmavaram section

Aug-18

2

CS

ROB in lieu of LC No.89 Between Mavinakere-Holenarsipur stations in Hassan Mysuru Section

Dec-18

3

CS

ROB in lieu of LC No.62 between Banapur -koppala stations (at Koppala yard) in Hubballi-Hosapete Section

Mar-19

4

CS

ROB in lieu of LC No.116 between Bangarpet - Maralahalli stations in Bengaluru-Jolarpet section.

Mar-19

5

CS

RUB in lieu of LC No.10 between Yesvantpur- Yelahanka stations in Yesvantpur- Yelahanka section

Mar-19

6

CS

RUB in lieu of LC No:131 between whitefield -Krishnarajapuram stations in Bengaluru-Jolarpet section

Mar-19

7

AW

ROB in lieu of LC No.108 between Nimbal-Indi road in Gadag -Hotgi section

Jan-19

8

AW

RUB in lieu of LC No. 65 between Wandal-basavanabagewadi rioad in Gadag -Hotgi section

Mar-19

9

AW

RUB in lieu of LC no.63 between Nittur -Sampige road stations in Tumakuru-Arisikere section.

Aug-18

10

AW

RUB in lieu of LC no.71 between Banasandra- Kardi stations in Tumakuru-Arisikere section

Feb-19

11

AW

RUB in lieu of LC no.80 between Kardi-Tiptur in Tumakuru-Arisikere- section.

Aug-18

12

AW

RUB in lieu of LC no.91 between Honnavalli road-Adihalli in Tumakuru-Arisikere section.

Jun-18

13

AW

RUB in lieu of LC no.92 between Honnavalli road-Adihalli in Tumakuru-Arisikere section.

May-18

14

AW

RUB in lieu of LC No.181 between Sasalu-Mayakonda stations in Chickjajur-Hubballi section

Dec-18

15

AW

RUB in lieu of LC No.187 between Kodaganur-Tolahunse stations in Chickjajur-Hubballi section.

Oct-18

16

AW

RUB in lieu of LC No.245 between Karajgi- Savanur stations in Chickjajur-Hubballi section

Feb-19

17

AW

RUB in lieu of LC No.250 between Karajgi- Savanur stations in Chickjajur-Hubballi section

Sept-18

18

AW

RUB in lieu of LC No.252 between Karajgi- Savanur stations in Chickjajur-Hubballi section

Sept-18

19

AW

RUB in lieu of LC No.255 between Savanur-Yelvigi stations in Chickjajur-Hubballi section

Jan-19

20

AW

RUB in lieu of LC No.256 between Savanur-Yelvigi stations in Chickjajur-Hubballi section

Sept-18

21

AW

RUB in lieu of LC No. 64 between Nimbal-Basavanabagewadi road stations in Gadag-Hotgi section.

Jan-19

22

AW

RUB in lieu of LC No.101 -A between minchnal-Nimbal stations in Gadag-Hotgi section.

Jan-19

23

AW

RUB in lieu of LC No.99 between pandavapura-srirangapatna stations in Ramanagaram-Mysuru section

Jan-19

24

CS

ROB in lieu of LC No.46 between Dharmapuri - Palakkodu stations in Salem-Yesvantpur section

Jun-18

25

CS

ROB in lieu of LC No.43 between Dharmapuri - Palakkodu stations in Salem-Yesvantpur section

Jul-18

26

CS

ROB in lieu of LC No.98 between Mulanur- Kuppam stations in Bengaluru-Jolarpet section

Dec-18

2019-20

1

CS

ROB in lieu of LC no:80 near Ibrahimpur with subway between Jumnal-Vijayapura stations in Gadag- Hotgi section

Feb-20

2

CS

ROB in lieu of LC No. 438 (Near Raybag) Raybag-Chinchli stations in Londa-Miraj section.

Feb-20

3

AW

RUB in lieu of LC No.234 between Byadgi-Haveri stations in Chickjajur-Hubballi section

Apr-19

4

AW

RUB in lieu of LC No.236 between Byadgi-Haveri stations in Chickjajur-Hubballi section

Apr-19

5

AW

RUB in lieu of LC No.241 between Haveri-Karajgi stations in Chickjajur-Hubballi section.

Apr-19

6

AW

RUB in lieu of LC No.254 between Savanur-Karajgi stations in Chickjajur-Hubballi section.

May-19

7

AW

RUB in lieu of LC No.219 between Ranebennuru-devaragudda stations in Chickjajur-Hubballi section.

Dec-19

8

AW

RUB in lieu of LCNo. 51 between Devarapalle-Hindupur stations in Baiyyappanahalli-Dharmavaram section.

Jul-19

2020-21

1

AW

RUB in lieu of LC No.260 ( At Yelvigi Yard ) Savanur-Yelvigi in Hubballi-Chickjajur - Doubling

May-20

2

AW

ROB in lieu of LCNo. 208 (In Harihar Yard)- 4 lanes in Hubballi-Chickjajur- Doubling.

Jun-20

3

AW

RUB in lieu of LC No.283 ( At Hubballi south Yard ) in Hubballi-Chickjajur - Doubling

Aug-20

4

AW

ROB in lieu of LC No. 68 (At Hanakere Yard) in Bengaluru- Mysuru Doubling

Aug-20

5

AW

RUB in lieu of LCNo. 34 ( At Oddarahalli yard ) in Yelahanka-Penukonda Doubling.

May-20

6

CS

LHS in lieu of LC no.136-A at Baiyyappanahalli in JTJ -SBC section.

Feb-21

7

AW

ROB in lieu of LCNo. 81 ( At Penukonda yard ) in Yelahanka-Penukonda Doubling.

Jun-20

8

CS

RUB in lieu of LC no.9 at hegde Nagar between YNK-CSDR stations in BYPL-DMM section.

Mar-21

2021-2022

1

CS

ROB in lieu of LC no.136-A with Subway at Baiyyappanahalli in JTJ -SBC section.

Nov-21

2

AW

ROB in lieu of LC No.243 (At Karajgi yard) in Hubballi-Chickjajur -Doubling

Feb-22

3

AW

RUB in lieu of LC No. 66 (Ammasandra yard) in Arsikere - Tumkur Doubling

Feb-22

4

CS

ROB in lieu of LC No. 381 between Belagavi - Desur stations (2 lanes)

Mar-22

5

CS

ROB in lieu of LC No. 91 with subway on Kudiyankuppam Road between Somanayakana patti - Jolar pettai stations (Railway Portion)

Mar-22

6

AW

ROB in lieu of LC No. 44 ( At Gauribidanur Yard) in Yelahanka-Penukonda Doubling

Mar-22

7

AW

RUB in lieu of LC No. 64 in Yelahanka-Penukonda Doubling

Mar-22

8

AW

RUB in lieu of LC No. 77 in Yelahanka-Penukonda Doubling

Mar-22

9

AW

RUB in lieu of LCNo. 350 in Miraj-Londa - Doubling.

Mar-22

2022-2023

1

CS

ROB in lieu of LC No. 38 with subway between Salem - Bengaluru City

Jun-22

2

CS

ROB in lieu of LC No. 79 with subway between Holenarsipura - Mavinkere stations

Oct-22

3

AW

RUB in lieu of LC No.224 under Hubballi-Chickjajur - Doubling project

Oct-22

4

CS

ROB in lieu of LC No. 81 with subway between mulvad - Vijayapura stations

Nov-22

5

AW

ROB in lieu of LC No.275 (At Kundgol yard) in Hubballi-Chickjajur- Doubling

Dec-22

6

AW

RUB at Km: 133/325 in Tumkur -Rayadurg New line project

Dec-22

7

AW

RUB at Km: 133/465 in Tumkur -Rayadurg New line project

Dec-22

8

AW

RUB at Km: 141/862 in Tumkur -Rayadurg New line project

Dec-22

9

AW

ROB at Km: 131/480 in Tumkur -Rayadurg New line project

Jan-23

10

AW

ROB at Km: 141/233 in Tumkur -Rayadurg New line project

Jan-23

11

AW

ROB at Km: 137/299 in Tumkur -Rayadurg New line project

Feb-23

12

AW

ROB at Km: 137/605 in Tumkur -Rayadurg New line project

Feb-23

13

AW

RUB at Km: 124/050 in Tumkur -Rayadurg New line project

Feb-23

14

AW

RUB at Km: 124/588 in Tumkur -Rayadurg New line project

Feb-23

15

AW

RUB at Km: 125/025 in Tumkur -Rayadurg New line project

Feb-23

16

AW

RUB at Km: 125/970 in Tumkur -Rayadurg New line project

Feb-23

17

AW

RUB at Km: 126/837 in Tumkur -Rayadurg New line project

Feb-23

18

AW

RUB at Km: 128/980 in Tumkur -Rayadurg New line project

Feb-23

19

AW

RUB at Km: 134/550 in Tumkur -Rayadurg New line project

Feb-23

20

CS

RUB in lieu of LC No. 5 at Mathikere

Feb-23

21

CS

ROB in lieu of LC No. 297 in Dharwad yard in Hubballi-Londa section .

Mar-23

22

CS

RUB in lieu of LC No.199 at Davanagere (1X7.5X3.0)

Mar-23

23

Dep

RUB in lieu of LC No.6 betweeen Channasandra -Yelahanka stations near Agara

Mar-23

24

CS

RUB in lieu of LC No. 11 at Jakkur

Mar-23

25

CS

ROB in lieu of LC No. 95 between Patchur-Mulanur stations (Railway portion)

Mar-23

2023-24

1

CS

Birur-Talaguppa - ROB in lieu of LC No.52 between Sivamogga -Kumsi stations.

Jun-23

2

AW

Yelahanka-Penukonda Doubling. RUB in lieu of LCNo.74 ( At Rangepalli yard )

Sep-23

3

AW

RUB at Br No. 92E in Gadag - Wadi New line project

Sep-23

4

CS

ROB in lieu of LC No. 3 (Near Hassan) (2 lanes)

Nov-23

5

CS

Ginigera - Munirabad - ROB in lieu of LC No. 72

Jan-24

6

AW

Gadag - Wadi section - ROB in lieu of LC No. 1A

Jan-24

7

CS

Shimogga - Kumsi - ROB in lieu of LC No. 49

Jan-24

8

AW

RUB in lieu of LC No. 73 in Ramanagaram - Mysuru Doubling

Mar-23

9

CS

ROB in lieu of LC No.37 in Kyatsandra station yard

Mar-23

2024-25

1

CS

ROB in lieu of LC No. 227 between Byadgi-Haveri stations ( 4 lanes )

May-24

2

AW

ROB in lieu of LC No.83 in Yelahanka - Penukonda doubling

Aug-24

3

AW

GDG - HG section: Construction of RUB in lieu of LC No.50

Dec-24

4

CS

ROB in lieu of LC No. 66 in Koppal - Ginigera section

Jan-25

5

AW

ROB 107 at 45/900-460/000 between Chikmagalur- Adihalli Stations - Chikmagalur- Belur NL

Feb-25

6

AW

ROB 124 at 49/000-100 between Chikmagalur- Adihalli Stations - Chikmagalur- Belur NL

Feb-25

7

AW

RUB 110A at 46/900-460/000 between Chikmagalur- Adihalli Stations - Chikmagalur- Belur NL

Feb-25

8

AW

ROB 92 at 44/700-800 between Hanmapur - Linganbandi Stations - Gadag-Wadi NL

Feb-25

9

CS

Subway in lieu of LC No. 91 with subway on Kudiyankuppam Road between Somanayakana patti-Jolar pettai stations.

Feb-25

10

AW

RUB114 at 47/500-600 between Chikmagalur- Adihalli Stations - Chikmagalur- Belur NL

Feb-25

11

CS

ROB in lieu of LC No. 34 in Bhadravati-Shivamogga section

Feb-25

12

CS

ROB in lieu of LC No. 92 between Jolarpet- Somanayakanapatti stations

Sept-24

13

AW

ROB No.137 @ 52/400-500 (Chikmagalur to Hadihali)

Feb-25

14

AW

ROB No 128 @ 50/000-100 (Chikmagalur to Hadihali)

Feb-25

15

AW

ROB No. 91 @ 30/841 (Kajjidhoni - Lokapur)

Feb-25

16

AW

ROB No. 82 @38/200-300 (Hanumapur to Linganbandi)

Feb-25

17

AW

ROB No. 89 @40/700-800 (Hanumapur to Linganbandi)

Feb-25

18

AW

RUB No. 134 @ 51/500-600 (Chikmagalur to Hadihali),

Feb-25

19

AW

RUB No. 95 @32/900 (Kajjidhoni - Lokapur)

Feb-25

20

AW

RUB No. 97A @ 34/050 (Kajjidhoni - Lokapur)

Feb-25

21

AW

RUB No. 76 @ 35/300-400 (Hanumapur to Linganbandi)

Feb-25

22

AW

RUB No. 79 @ 35-900/36-000(Hanumapur to Linganbandi)

Feb-25

23

AW

ROB no 181B @ 714/200-100 ( Kudachi to ugar)

Mar-25

24

AW

ROB no 185-B @ 714/800-900 ( Kudachi to ugar)

Mar-25

25

AW

ROB no.131 @ 50/600-700 (chikmagalur to Hadiihali

Mar-25

26

AW

RUB no.117 @ 47/800-900 (Chikmagalur to Hadihali),

Mar-25

27

AW

RUB no.120 @ 48/200-300 (Chikmagalur to Hadihali),

Mar-25

28

AW

RUB no.126 @ 49/500-600 (Chikmagalur to Hadihali),

Mar-25

29

AW

RUB no. 334 @ 65/100-200 (karatagi to Sindhanur)

Mar-25

30

AW

RUB no.343 @ 66/800-900 (karatagi to Sindhanur)

Mar-25

31

AW

RUB no. 348 @ 67/400-500 (karatagi to Sindhanur)

Mar-25

32

AW

RUB no. 140 @ 53/500-600 (Chikmagalur to Hadihalli)

Mar-25

33

AW

RUB no. 142 @ 54/600-700 (Chikmagalur to Hadihalli)

Mar-25

34

AW

RUB no. 95 @ 46/000-100 (Lingabandi to Kushtagi)

Mar-25

35

AW

RUB no. 97 @ 46/900-000 (Lingabandi to Kushtagi)

Mar-25

36

AW

RUB no. 99 @ 47/300-400 (Lingabandi to Kushtagi)

Mar-25

37

AW

RUB no. 101 @ 47/800-900 (Lingabandi to Kushtagi)

Mar-25

38

AW

RUB no. 102 @ 48/100-200 (Lingabandi to Kushtagi)

Mar-25

39

AW

RUB no. 107 @ 49/800-900 (Lingabandi to Kushtagi)

Mar-25

40

AW

RUB no. 112 @ 53/100-200 (Lingabandi to Kushtagi)

Mar-25

41

AW

RUB no. 114 @ 53/800-900 (Lingabandi to Kushtagi)

Mar-25

42

AW

RUB no. 116 @ 54/300-400 (Lingabandi to Kushtagi)

Mar-25

43

AW

RUB no. 120 @ 54/900-55/000 (Lingabandi to Kushtagi)

Mar-25

44

AW

ROB no. 105 @ 49/200-300 (Lingabandi to Kushtagi)

Mar-25

2025-26

1

AW

RUB 351 at 67/900-800 between Karatagi and Sindhanur Stations -Ginigera-Raichur NL

Jul-25

2

AW

RUB 352 at 68/200-300 between Karatagi and Sindhanur Stations -Ginigera-Raichur NL

Jul-25

3

AW

Construction of RUB in lieu of LC No.49 between Gadag Hotgi Section (AW)

Aug-25

4

AW

Yelahanka-Penukonda DL- RUB in lieu of LCNo. 83 ( At Penukonda yard ) AW

Aug-25

5

CS

SBC-JTJ Section-Proposed construction of ROB with subway in lieu of LC No. 120 at Km 298/100-200 between Maralahalli-Tyakal stations.

Aug-25

6

AW

ROB in lieu of LC No. 47 in Channapatna yard

Oct-25

 