InfrastructureMilestones
|
Year
|
New Lines (Km)
|
Gauge Conversion (Km)
|
Doubling (Km)
|
RVNL (Km)
|
|
| |
|
1999-2000
|
-
|
-
|
-
|
-
|
|
|
2000-2001
|
21
|
-
|
-
|
-
|
|
|
2001-2002
|
-
|
-
|
31
|
-
|
|
|
2002-2003
|
32
|
-
|
-
|
-
|
|
|
2003-2004
|
-
|
64
|
19
|
-
|
|
|
2004-2005
|
-
|
-
|
13
|
-
|
|
|
2005-2006
|
-
|
42
|
-
|
-
|
|
|
2006-2007
|
-
|
153
|
26
|
-
|
|
|
2007-2008
|
-
|
-
|
56
|
-
|
|
|
2008-2009
|
-
|
155
|
40
|
-
|
|
|
2009-2010
|
-
|
-
|
42
|
-
|
|
|
2010-2011
|
-
|
57
|
37
|
-
|
|
|
2011-2012
|
-
|
42
|
21
|
-
|
|
|
2012-2013
|
42
|
-
|
41
|
-
|
|
|
2013-2014
|
128
|
85
|
37
|
-
|
|
|
2014-2015
|
-
|
-
|
40
|
-
|
|
|
2015-2016
|
-
|
-
|
76
|
16
|
|
|
2016-2017
|
201
|
-
|
-
|
22
|
|
|
2017-2018
|
102
|
-
|
43
|
29
|
|
|
2018-2019
|
13
|
-
|
105
|
98
|
|
|
2019-2020
|
-
|
-
|
133
|
65
|
|
|
2020-2021
|
52
|
-
|
155
|
20
|
|
|
Total
|
591
|
598
|
915
|
250
|
|
Achievements Year wise
Achievements in 2002-2003
|
SL
|
Name of the Project
|
Section Commissioned
|
Length
(Km)
|
NL
|
Date of Commissioning
|
|
1
|
Dharmavaram-Penukonda via Puttaparthy
(53.10 km)
|
Sri Sathya Sai Prashanti Nilayam (Puttaparthy) -Dharmavaram
(32.30 km)
|
32
|
32
|
16.11.2002
|
|
Total
|
32
|
32
|
|
Achievements in 2003-2004
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length(Km)
|
GC
|
DL
|
Date of Commissioning
|
|
1
|
Hassan-Mangalore
(236 km)
|
Kankanadi- Kabakaputtur (44 km)
|
44
|
44
|
-
|
28.12.2003
|
|
2
|
Yeshwantpur-Salem
(197 km)
|
Yeshwantpur- Baiyyappanahalli
(20 km)
|
20
|
20
|
-
|
31.03.2004
|
|
3
|
Whitefield-Bangarpet - Kuppam (81.21 km)
|
Bangarpet- Bisanatham (19.025)
|
19
|
-
|
19
|
16.02.2004
|
|
Total
|
83
|
64
|
19
|
|
Achievements in 2004-2005
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length (Km)
|
DL
|
Date of Commissioning
|
|
1
|
Whitefield-Bangarpet- Kuppam
(81.21 km)
|
Bisanatham-Kuppam (12.75 km)
|
13
|
13
|
10.11.2004
|
|
Total
|
13
|
13
|
|
Achievements in 2005-2006
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length (Km)
|
GC
|
Date of Commissioning
|
|
1
|
Hassan- Mangalore(236 km)
|
Kabakaputtur-Subramanya Road (42 km)
|
42
|
42
|
22.07.2005
|
|
Total
|
42
|
42
|
|
Achievements in 2006-2007
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length
(Km)
|
GC
|
DL
|
Date of Commissioning
|
|
1
|
Hassan- Mangalore (236 km)
|
Sakleshpur- Subramanya Road (55 km)
|
55
|
55
|
-
|
05.05.2006
|
|
2
|
Sholapur- Gadag(330 km)
|
Bijapur-Basavanabagewadi-Bagalkot(98 km)
|
98
|
98
|
-
|
16.09.2006
|
|
3
|
Tornagallu- Hospet(32 km)
|
Tornagallu- Bayaluvoddigere
(14 km)
|
14
|
-
|
14
|
31.12.2006
|
|
4
|
Bangalore- Ramanagaram (44 km)
|
Bangalore-Kengeri (12 km)
|
12
|
-
|
12
|
27.02.2007
|
|
Total
|
179
|
153
|
26
|
|
Achievements in 2007-2008
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length
(Km)
|
DL
|
Date of Commissioning
|
|
1
|
Tornagallu-Hospet (32 km)
|
Bayaluvoddigere- Kariganuru (13 km)
|
13
|
13
|
18.02.2008
|
|
2
|
Bangalore - Ramanagaram (44 km)
|
Kengeri-Bidadi
(17 km)
|
17
|
17
|
08.12.2007
|
|
3
|
Yeshwantpur- Tumkur (70 km)
|
Yeshwantpur - Golhalli
(20 km)
|
20
|
20
|
06.10.2007
|
|
Total
|
50
|
50
|
|
Achievements in 2008-2009
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length (Km)
|
GC
|
DL
|
Date of Commissioning
|
|
1
|
Sholapur-Gadag (330 km)
|
Bagalkot-Gadag (93 km)
|
93
|
93
|
-
|
06.12.2008
|
|
2
|
Mysore- Chamarajanagar(62 km)
|
Mysore-Nanjangud (26 km)
|
26
|
26
|
-
|
09.06.2008
|
|
Nanjangud- Chamarajanagar (36 km)
|
36
|
36
|
-
|
11.11.2008
|
|
3
|
Tornagallu- Hospet (32 km)
|
Kariganuru-Hospet (23 km)
|
23
|
-
|
23
|
05.10.2008
|
|
4
|
Bangalore-Ramanagaram (44 km)
|
Bidadi-Ramanagaram(14 km)
|
14
|
-
|
14
|
06.11.2008
|
|
5
|
Yeshwantpur- Tumkur (70 km)
|
Golhalli- Nidavanda (21km)
|
21
|
-
|
21
|
26.05.2008
|
|
Total
|
213
|
155
|
58
|
|
Achievements in 2009-2010
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length (Km)
|
DL
|
Date of Commissioning
|
|
1
|
Yeshwantpur - Tumkur (70 km)
|
Nidavanda - Tumkur
(23 km)
|
23
|
23
|
10.04.2009
|
|
2
|
Hubli-Hebsur
(16.632 km)
|
Hubli - Hebsur
(16.632 km)
|
17
|
17
|
07.02.2010
|
|
Total
|
40
|
40
|
|
Achievements in 2010-2011
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length
(Km)
|
GC
|
DL
|
Date of Commissioning
|
|
1
|
Shimoga-Talguppa (97 km)
|
Shimoga-Anandapuram (56 km)
|
56
|
56
|
-
|
10.07.2010
|
|
2
|
Ramanagaram-Mysore (94 km)
|
Ramanagaram – Chennapatna (12 km)
|
12
|
-
|
12
|
20.11.2010
|
|
Mysore-Naganahalli (9km)
|
9
|
9
|
29.11.2010
|
|
3
|
Dharwad-Kambarganvi(28 km)
|
Dharwad-Mugad
(15.88 km)
|
16
|
-
|
16
|
April 2010
|
|
Total
|
94
|
57
|
37
|
|
Achievements in 2011-2012
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length (Km)
|
GC
|
DL
|
Date of Commissioning
|
|
1
|
Shimoga- Talguppa(97 km)
|
Anandapuram-Talguppa (42 km)
|
42
|
42
|
-
|
10.07.2011
|
|
2
|
Arsikere- Birur
(45 km)
|
Arsikere-Devanur(23 km)
|
23
|
-
|
23
|
30.07.2011
|
|
Total
|
65
|
42
|
23
|
|
Achievements in 2012-2013
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length (Km)
|
DL
|
NL
|
Date of Commissioning
|
|
1
|
Hassan- Bangalore via shravanabelagola
(167 km)
|
Hassan- Shravanabelagola
(42 km)
|
42
|
-
|
42
|
July 2012
|
|
2
|
Dharwad- Kambarganvi (28 km)
|
Mugad-Kambarganvi (12 km)
|
12
|
12
|
-
|
28.04.2012
|
|
3
|
Arsikere-Birur
(45 km)
|
Devanur-Ballakere (10 km)
|
10
|
10
|
-
|
19.06.2012
|
|
Ballakere-Birur(12 km)
|
12
|
12
|
09.11.2012
|
|
4
|
Ramanagaram- Mysore (94 km)
|
Channapatna- Settihalli (7 km)
|
7
|
7
|
-
|
30.03.2013
|
|
Total
|
83
|
41
|
42
|
|
Achievements in 2013-2014
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length
(Km)
|
GC
|
DL
|
NL
|
Date of Commissioning
|
|
1
|
Hassan- Bangalore via Shravanabelagola
(167 km)
|
Chikbanavar- Nelamangala
(14 km)
|
14
|
-
|
-
|
14
|
29.04.2013
|
|
2
|
Kadur-Chikmagalur-Sakleshpur (97 km)
|
Kadur-Chikmagalur (46 km)
|
46
|
-
|
-
|
46
|
19.11.2013
|
|
3
|
Kottur-Harihar(66 km)
|
Kottur-Harihar
(66 km)
|
66
|
-
|
-
|
66
|
30.03.2014
|
|
4
|
Kolar-Chikballapur (85km)
|
Kolar-Chikballapur
(85 km)
|
85
|
85
|
-
|
-
|
08.11.2013
|
|
5
|
Ramanagaram- Mysore (94 km)
|
Maddur- Hanakere- Mandya (19 km)
|
19
|
-
|
19
|
-
|
21.08.2013
|
|
6
|
Birur-Shivani(29 km)
|
Birur- Nagavangala(9 km)
|
9
|
-
|
9
|
-
|
15.06.2013
|
|
7
|
Birur-Shivani (29 km)
|
Nagavangala- Ajjampur (9 km)
|
9
|
-
|
9
|
-
|
15.06.2013
|
|
Total
|
249
|
85
|
37
|
127
|
|
Achievements in 2014-2015
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length
(Km)
|
DL
|
Date of Commissioning
|
|
1
|
Ramanagaram-Mysore (94 km)
|
Settihalli-Maddur (11 km)
|
11
|
11
|
02.07.2014
|
|
Mandya-Yeliyur(8 km)
|
8
|
8
|
14.08.2014
|
|
2
|
Birur-Shivani (29 km)
|
Ajjampur-Shivani (11 km)
|
11
|
11
|
17.02.2015
|
|
3
|
Shivani- Hosadurga(10 km)
|
Shivani- Hosadurga (10 km)
|
10
|
10
|
17.02.2015
|
|
Total
|
40
|
40
|
|
Achievements in 2015-2016
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length
(Km)
|
DL
|
Date of Commissioning
|
|
1
|
Ramanagaram-Mysore (94 km)
|
Yeliyur-Naganahalli
(28 km)
|
28
|
28
|
30.11.2015
|
|
2
|
Hosadurga- Chikjajur(30 km)
|
Hosadurga- Chikjajur (30 km)
|
30
|
30
|
29.10.2015
|
|
3
|
Yelahanka- Chennasandra (13 km)
|
Yelahanka- Chennasandra (13 km)
|
13
|
13
|
31.01.2016
|
|
4
|
Yeshwantpur- Yelahanka DL (7 km)
|
Yeshwantpur- Yelahanka DL(7 km)
|
7
|
7
|
31.03.2016
|
|
5
|
Hospet-Hubli-Londa-Vasco-da-gama (352.58 km) (being executed by RVNL)
|
Haralapur-Sompur-Bannikoppa (16.48 km)
|
16
|
16
|
30.01.2016
|
|
Total
|
94
|
94
|
|
Achievements in 2016-2017
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length (Km)
|
DL
|
NL
|
Date of Commissioning
|
|
1
|
Rayadurga- Tumkur(207 km)
|
Rayadurga-Kalyanadurga (40 km)
|
40
|
-
|
40
|
31.12.2016
|
|
2
|
Rayadurga- Tumkur (207 km)
|
Kalyanadurga- Kadiridevarapalli
|
23
|
-
|
23
|
31.03.2017
|
|
3
|
Hassan- Bangalore via Shravanabelagola (167 km)
|
Nelamangala- Shravanabelagola
(111 km)
|
111
|
-
|
111
|
26.03.2017
|
|
4
|
Munirabad (Ginigera) -Raichur (165 km)
|
Ginigera- Chikkabenakal
(27 km)
|
27
|
-
|
27
|
31.03.2017
|
|
5
|
Hospet-Hubli-Londa-Vasco-da-gama (352.58 km)
(being executed by RVNL)
|
Kambarganvi- Alnawar (12 km)
|
12
|
12
|
-
|
30.04.2016
|
|
Bannikoppa- Bhanapur (11 km)
|
11
|
11
|
-
|
25.12.2016
|
|
Total
|
224
|
23
|
201
|
|
Achievements in 2017-2018
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length (Km)
|
DL
|
NL
|
Date of Commissioning
|
|
1
|
Bidar- Gulbarga (123 km)
|
Homnabad- Gulbarga (72.40 km)
|
72
|
-
|
72
|
29.10.2017
|
|
2
|
Bagalkot- Kudachi(142 kms)
|
Bagalkot-Khajdoni (30 km)
|
30
|
-
|
30
|
25.10.2017
|
|
3
|
Hospet-Hubli-Londa-Vasco-da-gama (352.58 km)
(being executed by RVNL)
|
Shivathan-Londa- Tinaighat (16.46 km)
|
16
|
16
|
-
|
30.05.2017
|
|
Bhanapur-Koppal
(12.23 km)
|
12
|
12
|
-
|
13.06.2017
|
|
4
|
Hotgi-Kudgi-Gadag(284 km)
|
Lachyan-Minchinal (43 km)
|
43
|
43
|
-
|
29.03.2018
|
|
Total
|
173
|
71
|
102
|
|
Achievements in 2018-2019
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length
(Km)
|
DL
|
NL
|
Date of Commissioning
|
|
1
|
Munirabad (Ginigera) -Raichur (165 km)
|
Chikkabenakal -Gangavathi (13 km)
|
13
|
-
|
13
|
04.03.2019
|
|
2
|
Arsikere-Tumkuru (96 km)
|
Arsikere-Karadi (36km)
|
36
|
36
|
-
|
29.11.2018
|
|
3
|
Hubli-Chikjajur (190 km)
|
Chikjajur-Tolahunse
|
37
|
37
|
-
|
11.12.2018
|
|
4
|
Hospet-Hubli-Londa-Vasco-da-gama (352.58 km)
(being executed by RVNL)
|
Koppal-Hospet(27.73)
|
28
|
28
|
-
|
26.12.2018
|
|
Devaraya – Shivathan (8.12 km)
|
8
|
8
|
-
|
07.05.2018
|
|
Koppal-Ginigera-Hosapete (27.73 Km)
|
28
|
28
|
-
|
26.12.2018
|
|
Hebsur-Annigeri(16.38)
|
16
|
16
|
-
|
05.04.2018
|
|
Annigeri-Hulkoti-Binkadakatti (17.60km)
|
18
|
18
|
-
|
|
|
5
|
Hotgi-Kudgi-Gadag
(284 km)
|
Jumnal-Minchinal
(30 Km)
|
30
|
30
|
-
|
14.03.2019
|
|
Total
|
214
|
201
|
13
|
|
Achievements in 2019-2020
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length
(Km)
|
DL
|
Date of Commissioning
|
|
1
|
Arsikere-Tumkuru
(96 km)
|
Gubbi-Tumkuru (18 km)
|
18
|
18
|
29.05.2019
|
|
2
|
Arsikere-Tumkuru
(96 km)
|
Karadi-Banasandra
(11 km)
|
11
|
11
|
22.02.2020
|
|
3
|
Yelahanka- Penukonda
(122.55 km)
|
Makalidurga- Devarapalli
( 36 km)
|
36
|
36
|
05.04.2019
|
|
4
|
Hotgi-Kudgi- Gadag (284 km)
|
Wandal-Mulvad(27 km)
|
27
|
27
|
29.05.2019
|
|
5
|
Hotgi-Kudgi- Gadag (284 km)
|
Mulvad-Jumnal (12 km)
|
12
|
12
|
12.11.2019
|
|
6
|
Hubli-Chikjajur
(190 km)
|
Davangere- Harihar
(13 km)
|
13
|
13
|
27.11.2019
|
|
7
|
Miraj-Londa
(186 km)
|
Ghataprabha- chikkodi
(15 km)
|
15
|
15
|
11.12.2019
|
|
8
|
Hospet-Hubli- Londa-Vasco-da- gama (352.58 km) (being executed by RVNL)
|
Alnawar- Devarayi
(20.73 km)
|
21
|
21
|
29.05.2019
|
|
9
|
Hospet-Hubli-Londa-Vasco-da-gama (352.58 km) (being executed by RVNL)
|
Hubli by-pass (20.60 km)
|
21
|
21
|
06.09.2019
|
|
10
|
Hospet-Hubli-Londa-Vasco-da- gama (352.58 km) (being executed by RVNL)
|
Binkadakatti-Harlapur (23.17 km)
|
23
|
23
|
12.02.2021
|
|
Total
|
198
|
198
|
|
Achievements in 2020-2021
|
SL
|
Name of the Projects
|
Section Commissioned
|
Length
(Km)
|
DL
|
NL
|
Date of Commissioning
|
|
1
|
Hotgi-Kudgi-Gadag (284 km)
|
Lachyan-Hotgi
(33 km)
|
33
|
33
|
-
|
25.07.2020
|
|
2
|
Munirabad-(Ginigera) -Raichur (165 km)
|
Gangavathi-Karatagi (26 Km)
|
26
|
-
|
26
|
31.05.2020
|
|
3
|
Third Coaching Terminal at Baiyyappanahalli
|
Third Coaching Terminal at Baiyyappanahalli
|
24
|
-
|
24
|
30.06.2020
|
|
4
|
Hospet-Hubli- Londa-Vasco-da- gama (352.58 km) (being executed by RVNL)
|
Unkal - Dharwad
|
17
|
17
|
-
|
18.10.2020
|
|
5
|
Miraj-Londa
(186 km)
|
Chikodi - Raybag (14 km)
|
14
|
14
|
-
|
16.12.2020
|
|
6
|
Hubli-Chikjajur
(190 km)
|
Harihar - Devargudda (31 km)
|
31
|
31
|
-
|
02.01.2021
|
|
7
|
Arsikere-Tumkuru
(96 km)
|
Gubbi - Nittur
(9 km)
|
9
|
9
|
-
|
30.01.2021
|
|
8
|
Yelahanka-Penukonda (122.55 km)
|
Yelahanka - Makalidurga(36 km)
|
36
|
36
|
-
|
24.02.2021
|
|
9
|
Hubli-Chikjajur
(190 km)
|
Hubli - Hubli South (4 km)
|
4
|
4
|
-
|
24.02.2021
|
|
10
|
Hospet-Hubli- Londa-Vasco-da- gama (352.58 km) (being executed by RVNL)
|
Hubli - Unkal along with Hubli yard
|
3
|
3
|
-
|
22.02.2021
|
|
11
|
Miraj-Londa
(186 km)
|
Raybag - Kudachi (17 km)
|
17
|
17
|
-
|
28.03.2021
|
|
12
|
Hubli-Chikjajur
(190 km)
|
Tolahunse - Davangere(10 km)
|
10
|
10
|
-
|
17.03.2021
|
|
Total
|
224
|
174
|
50
|
|