IMPORTANT MILESTONES OF THIS LAND MARK SHED

ØRB Sanction for the shed                            :   Oct’ 1996

ØSanction for 50 Locos Homing                     :    1996-97

vSanction Cost                    :         15.26 Crores.

vRevised Estimate               :         22.41 Crores.     

ØCompletion of shed construction                  :   June’1999

ØReceipt of 1st  Imported WDG4 12005           :   15-04-1999

ØReceipt of 1st Imported WDP4 20000             :   25-07-2001

ØReceipt of 1st DLW built WDG4 12022            :   20-05-2002

ØReceipt of 1st DLW built WDP4 20011            :   01-06-2003

ØCommissioning of 50th loco 12039                 :   09-07-2003

ØCommissioning of 75th loco 12062                 :   15-08-2004

ØSanction for Expansion from                           :    2005-2006

50 to 100 Locos

vSanction Cost                   :         13.00 Crores.

vRevised Estimate              :         18.97 Crores.     

vCompleted                         :         April -2017.

ØCommissioning of 100th loco 12081               :   01-04-2006

ØShed Expansion from 100 to 150 locos            :    2007-2008

vSanction Cost                   :         12.96 Crores.

vRevised Estimate              :         26.07 Crores.     

vCompleted                         :         March -2017.

ØCommissioning of 125th loco 12088              :   21-01-2007

ØCommissioning of 150th loco 12127              :   23-09-2007

ØShed expansion from 150 to 200 locos          :    2010-2011

vSanction Cost                   :         18.70 Crores.

vDetailed Estimate             :         37.6 Crores.

vCompleted                         :         July -2020.

 

ØCommissioning of First WDG4D                     :    30-01-2016 

Loco no.70441   

ØCommissioning of 221th loco 70516            :   01-08-2016

(Note: 20 Dual Cab locos were immediately transferred to other Zones).

             ØCommissioning of First WDP4D                   :   01-02-2018 loco no.40519

ØIMS Certification of shed                              :   26.09.2019

Ø5S Certification of shed                                :   09.10.2019

ØReceipt of 235thHHP Locomotive 12434   :   02.04.2021 

(From NWR)                      

ØFirst HHP  diesel locomotive 12001 WDG4 :   27.12 2021 

vRe- inducted after periodic over hauling by Diesel loco shed Hubballi. 

 

ØSanction for 50 Locos Homing Electrical Locos :   2022-23

v   Sanction Cost       :  25.64 Crores.

 

ØFirst 3 phase Electric MU locos (“Ghataprabha” & “Malaprabha”) loco no. 43045 & 43046  was commissioned on 26.09.2022.

ØCommissioning of 50thAC locomotive 38198 WAG9HC: 17th Jan-24.