Press Release No. 154 06-07-2020
Hubballi
Press Release No. 154, COMMISSIONER OF RAILWAY, SAFETY INSPECTS RAILWAY ELECTRIFICATION WORKS BETWEEN RAYADURGA AND TALAKU SECTION (48 ROUTE KM) OF MYSORE DIVISION OF SWR

प्रेस विज्ञप्तिPress Release No. 154  Dt: 30.06.2020

COMMISSIONER OF RAILWAY, SAFETY INSPECTS RAILWAY ELECTRIFICATION WORKS BETWEEN RAYADURGA AND TALAKU SECTION (48 ROUTE KM) OF MYSORE DIVISION OF SWR

Electrification works o­n 48 Route Km of section between Rayadurga and Talaku o­n Mysuru Division of SWR. This section is part of the 184 Route Km of Ballari – Chikjajur electrification.  CRS inspection and speed trial of 48 Rkm electrified section between Rayadurga and Talaku  of Mysuru division of SWR was done o­n 30.06.2020 by  Shri A K Rai, Commissioner of Railway Safety, Southern Eastern Region.  He is looking after Southern Region also, after retirement of Shri K. Manohar in May 2020.  This work is being executed by Rail Vikas Nigam Ltd.

Electrification of Section between Ballari to Rayadurga (53 Rkm) was completed in Dec 2019. Electrification of Thornagallu and Hosapete has been completed in Feb 2020

As envisioned in Union Budgets 2019 & 2020   Indian Railways is aiming to achieve the full electrification of its tracks in the next three to four years.  o­n SWR aprox 802 Rkm of electrification has been targeted for completion in this financial year.

Last year 147 Route Km of Railway track of SWR has been electrified. The sections which were energised include Ballari – Rayadurga (53 Rkm), Toranagallu - Ranjithpura (23 Rkm) Baiyappanahalli – Anekal (37 RKm) & Toranagallu – Kariganur (34 RKms). 


During the inspection, 3 power line crossings (2 between Talaku and Bommagundanakere and 1 between Bommagundanakere and Molakalmuru), 4 LC gates o­n the section and 4 stations (Talaku, Bommagundanakere, Molakalmuru & Rayadurga) were covered.

Over Head Equipment o­n the section i.e., foundations (1076 Nos.), mast erection & grouting (888 Nos.) portal/boom erection (18 Nos), bracket erection, wiring (104 shot) SED & TW checking were inspected.  Short circuit test was also conducted o­n the section.

Shri B G Mallya, PCEE, Shri Ajay Kumar, PCSTE, Smt Aparna Garg, DRM/MYS, Shri Himanshu Sharma, GM/EL/RVNL and other Branch officers of Mysuru division accompanied CRS during the inspection.  After completion of speed trial and inspection of the section and safety equipment at stations o­n this section, CRS will consider the proposal for Authorization of electrification of this line for passenger traffic.

Electrification will significantly improve mobility of trains o­n SWR and strengthen Rail network in Karnataka.  In addition to reduction in pollution, energy efficiency of Railway will improve due to shift from fossil fuel to electricity and save substantial foreign exchange.

                   

                       


                                                                                           Chief Public Relations Officer

                                                                              South Western Railway, Hubballi





  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.