Press Release No. 17021-07-2020
Hubballi
Press Release No. 170, SHRI SURESH ANGADI, HON’BLE MINISTER OF STATE OF RAILWAYS REVIEWS LONDA-MIRAJ AND GADAG-HOTGI DOUBLING PROJECT

प्रेस विज्ञप्तिPress Release No. 170  Dt: 19.07.2020

SHRI SURESH ANGADI, HON’BLE MINISTER OF STATE

 OF RAILWAYS REVIEWS LONDA-MIRAJ AND GADAG-

HOTGI DOUBLING PROJECT

Shri Suresh Angadi, Hon’ble Minister of State of Railways conducted a review meeting with General Managers and other officials of South Western Railway, Central Railway and South Central Railway through Video Conference o­n 17.07.2020. 

During the meeting, Shri Angadi reviewed the progress of Miraj-Londa and Gadag-Hotgi double line project. 

The 186 Km of Londa-Miraj doubling project is being executed in 7 phases.  In Phase-I, 16 Km of doubling between Ghataprabha and Chikkodi Road has been completed and commissioned during December, 2019.

 In Phase-II, the doubling  of 31 Km between Chikkodi Road-Raybag-Chinchli-Kudachi, in Phase-III, 25 Km of Khanapur-Desur-Belagavi doubling, in Phase-IV 25 Km of Londa-Khanapur doubling, in Phase-V, 27 Km of Belagavi-Suldhal doubling, in Phase-VI, 30 Km of Suldhal- Ghataprabha doubling,  in Phase-VII, 33 Km of Kudachi-Miraj doubling works are being executed. Due to COVID-19, work has slowed down from March, 2020. Work recommenced from last week of June, 2020 with limited number of manpower, so as to maintain social distancing. 

Shri Suresh Angadi instructed the Officials to expedite this double line project along with electrification and to complete in two years.

          Road Over Bridge works at Belagavi and Raybag area were also reviewed and Hon’ble MoSR instructed to complete the works in time bound manner.   

Shri Suresh Angadi also reviewed the 284 Km doubling work of Gadag-Hotgi.  Already 115 Km of doubling has been completed.  Another 33 Km between Lachyan and Hotgi doubling is also expected to be commissioned shortly.   o­nce this 33 Km is commissioned a total 148 Km of line from Hotgi to Wandal will become double line.   Shri Suresh Angadi instructed the Officials to complete the remaining  double line work by 2022. 

Shri Ajay Kumar Singh, GM/SWR; hri K.C. Swami, Chief Administrative Officer, Construction; Shri B.G. Mallya, Principal Chief Electrical Engineer; Shri Prem Narayan, Chief Engineer, Construction and Shri T.V. Bhushan, Chief Engineer, Construction, Hubballi from South Western Railway have  attended the Video Conference.


                                                                                           Chief Public Relations Officer

                                                                              South Western Railway, Hubballi





  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.