Hubballi
Press Release No. 320, HUBBALLI DIVISION COMPLETED THE RE-BUILDING OF WATER WAY BRIDGE IN HUBBALLI - GADAG SECTION

दक्षिण पश्चिम रेलवे/ SOUTH WESTERN RAILWAY

प्रेस विज्ञप्ति/ Press Release No. 320  Dt: 22.12.2020      

HUBBALLI DIVISION COMPLETED THE RE-BUILDING OF

 WATER WAY BRIDGE IN HUBBALLI - GADAG SECTION

            Hubballi Division completed the rebuilding of water way bridge in Hebsur recently. Bridge No. 9 of span 6.1m in Hubballi – Gadag Railway line at Hebsur which was old and in Run – down condition was replaced with new bridge of newest loading standard.

            Bridge No. 9 which was built during British Era o­n Hubballi – Gadag railway line was observed to be showing signs of deterioration during regular inspection of Railway officials. Hence, it was immediately supported with C-C cribs and strengthened. Further, a new bridge was designed and planned to be replaced as a permanent measure. The RCC boxes were casted at location and were planned to push below the running track. But the site posed a very typical challenge as the soil in area has a thick layer of Black cotton soil which has very poor bearing capacity. Another field level problem was that the site at which the work was to be done was the lowest point of the area due to which it was perpetually water logged. This made taking men, material and machinery to the site extremely difficult.

            The site was drained out by making trenches and pits. Moreover, the approach to the site was made by using released railway concrete sleepers during the month of October and November 2020. The work was taken up under the guidance of Shri Vipul Kumar, Principal Chief Engineer and Shri Arvind Malkhede, Divisional Railway Manager in the month of December 2020. RCC boxes were pushed below the running railway line and the work was completed.  Shri Arvind Malkhede said that the Hubballi Division team led by Shri Vinayak Padalkar, Divisional Engineer took up the work o­n war footing and in a mission mode to complete the work at the earliest.

            Shri Ajay Kumar Singh, GM/SWR appreciated the officers and staff for successfully completing the work even under difficult conditions and said that Railway is working relentlessly towards enhancing passenger safety by strengthening of tracks and bridges.


                                                                   Chief Public Relations Officer                                                                    South Western Railway, Hubballi





  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.