Press Release No. 330 29-12-2020
Hubballi
Press Release No. 330, NEWLY CONSTRUCTED LIMITED HEIGHT SUBWAY AT LONDA YARD

दक्षिण पश्चिम रेलवे/ SOUTH WESTERN RAILWAY

प्रेस विज्ञप्ति/ Press Release No. 330  Dt: 29.12.2020      

NEWLY CONSTRUCTED LIMITED HEIGHT SUBWAY AT LONDA YARD

South Western Railway is o­n a mission mode of eliminating Level Crossing Gates over the Zone by construction of Road Over Bridges (ROB), Road Under Bridges (RUB) and Limited Height Subways (LHB). During the previous year, 6 ROBs and 77 RUBs/LHBs were constructed in the zone.

During the Inspection by Shri Ajay Kumar Singh, GM/SWR at Londa o­n 29.09.2020, the local public represented the difficulties faced by them due to the closure of the LC Gate No.343 at Londa Yard for train movements. They requested Railways to construct a RUB/LHB and to help the local residents who were forced to take a circuitous route of 3 Km due to closure of LC gate due to shunting movements etc. in the yard.  Around 250 families living o­n the other side of town lacked direct access to main Town of Londa for nearly last 7 decades. Pedestrian crossing over the track due to closure of LC gate for train movement was a safety issue requiring immediate action by Railways.

As instructed by GM/SWR, under the initiative of Shri Arvind Malkhede, Divisional Railway Manager, Hubballi, Engineering Branch took up the work of construction of Limited Height subway in Oct 2020. All the pre-requisite and mandatory paper work related to sanctioning of estimate, general arrangement drawings, temporary arrangement of drawings and fixing of  contractual agency was completed within least  possible  period of 30 days. Work of earth excavation, casting of reinforced cement concrete work started o­n 29.10.2020.

Approval of District authorities was received in Nov 2020, within 10 days of applying the same.  Work started by inserting 25 nos. of RCC boxes for a length of 40 metres.  The cost of this subway is Rs. 6.12 Crores.  Physical work took just 50 days. Hubballi Division executed the construction o­n a war footing basis and work could be completed and opened for traffic today o­n 90thday (29.12.2029) from conception. This project which usually takes 24 to 30 months has been completed in 90 days which is a new record in Indian Railways.

The entire project has been executed by the Engineering team of Hubballi Division led by Shri P Mahender, Sr. Divisional Engineer/Coordination. Shri Neeraj Bapna, Senior Divisional Engineer/ West has taken up the work o­n war footing basis for the public. The work was taken up as part of the doubling project between Londa – Vasco.

Shri Ajay Kumar Singh, GM/SWR has congratulated the Officers and staff for completing the RUB/LHB in a record time of 90 days. Shri Singh also appreciated the District authorities for their speedy clearance so that the work could be taken up expeditiously.


                                                                   Chief Public Relations Officer                                                                    South Western Railway, Hubballi





  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.