Press Release No. 33704-01-2021
Hubballi
Press Release No. 337, DOUBLE LINE TRACK BETWEEN HARIHAR AND DEVARAGUDDA STATIONS (31 Km) COMMISSIONED

दक्षिण पश्चिम रेलवे/ SOUTH WESTERN RAILWAY

प्रेस विज्ञप्ति/ Press Release No. 337  Dt: 03.01.20201     

DOUBLE LINE TRACK BETWEEN HARIHAR AND

 DEVARAGUDDA STATIONS (31 Km) COMMISSIONED

Newly laid double line between Harihar and Devaragudda Stations (31 Kms) o­n South Western Railway, Mysuru Division was commissioned o­n 02.01.2021.  This double line between Harihar and Devaragudda Stations is part of the 190 Km doubling between Hubballi and Chikjajur.  81 Km have so far been commissioned in this section which includes 37 Km between Chikjajur-Tolahunse, commissioned in Oct 2018 and 13 Km between  Davangere-Harihar, commissioned in Nov 2019.

Commissioner of Railway Safety (CRS)/ Southern Circle, Bengaluru completed statutory inspection of newly laid double line between Harihar  and Devaragudda stations (31 Km)  o­n 23.12.2020 & 24.12.2020  .After completion of all Non interlocking and interlocking  works ,double line between Harihar and Devaragudda Station has been opened to traffic from 02.01.2020.

On completion of CRS inspection Non Interlocking works started from 29.12.20 and were completed o­n 02.01.2021.  The following works were completed enabling commissioning of the section o­n 2.2.2021

1.  Kumarapatna siding (9 routes) was commissioned o­n 29.12.20 with yard remodelling and doubling o­n both end with EI alteration.

2.  Chalgeri (32 routes) was commissioned o­n 30.12.20 with yard remodelling with doubling o­n both end with EI alteration.

3.  Ranebennu (34 routes) commissioned o­n 31.12.20 with yard remodelling from exg 2 rd to 4 rd alongwith doubling o­n both end with EI alteration.

4.  Devaragudda (32 routes) was commissioned o­n 01.01.21 with yard remodelling from exg 2 rd to 4 rd alongwith doubling o­n Ranebennur end with EI alteration.

5.  Harihar (141 routes) commissioned o­n 02.01.21with major yard remodelling from exg 5 rd to 7rd with 24 additional points 33 new track ckts along wth doubling towards KMPS.

Salient features of Harihar – Devaraguda Section:

1.One additional running line, and 1 additional stabling line and 2 full length shunting necks are added in Harihar yard. Major yard remodelling work is done in Harihar yard spanning a length of 2.5 km.   Total – 46 points were   inserted, which was mammoth work under traffic conditions.

2.Two additional running  lines were  added in Devargudda and o­ne additional line each at Kumarapatnam, Chalgeri and Ranebennur were  also  been added as a part of this  doubling.

3.  2 new High Level Island Platforms in Chalgeri yard of 450m length each  and 2 no.  High Level  end PF of each 540 m length at  Devaragudda yard have  been  constructed  . PF extension/ Widening  of 170 m length of two PFs in Harihar, o­ne PF of 120 m length in Chalegere, and two PFs of 100 m each  in Ranebennur. Trolley path at both side of PF have been paved with  concrete for way  movement of trollies/wheel chairs . 

4.  4 Level crossing gates  closed after  construction of ROB / RUB work in the section.

LC -208 and 213 closed by construction of ROB,

LC-219 and 221 closed  by construction of RUB. 

5.  Two new RUBs at 77 and 82 were also constructed responding to  public  demand as a part of doubling

6.  The total cost of Project is Rs. 298 crore.

7.  One important Bridge of 16 span constructed o­n Tungabandra river.

The work of doubling of the section was planned by Shri K C Swami, CAO/CN. The plan was meticulously executed by Shri Narayan Rao, CE/CN/North and Shri Shantiram, CSTE/CN and other officials of Construction Organisation.

Shri, Rahul Agarwal, Divisional Railway Manager of Mysuru Division, monitored the work of interlocking along with Officers and staff of Mysuru division who worked continuously for early commissioning of the section.

Shri Ajay Kumar Singh, GM/SWR commended the work saying that it will improve Mobility greatly. Infrastructure development was given big thrust with this doubling to enable the zone to run faster trains.  Shri Singh informed that the work of the remaining section is in full swing and targeted to be commissioned in in next year. He said that yard remodeling works done at Harihar with team work and synchronisation of  all branches of Railway . This remodeling gives good flexibility to yard operations at Harihar. Keeping passenger convienence at mind many passenger amenities also have been provided in this work.

Also responding to public demand and representations of Elected representatives, 2 Road Over Bridges and 2 Road under bridges have been constructed in this section that will facilitate road users and will enhance safety.

                                                                   Chief Public Relations Officer                                                                    South Western Railway, Hubballi





  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.