Press Release No. 33804-01-2021
Hubballi
Press Release No. 338, THE SUBWAY AT LONDA IS LIKELY TO ENTER IN LIMCA BOOK OF RECORDS FOR IT’S COMPLETION IN RECORD PERIOD OF 90 DAYS

दक्षिण पश्चिम रेलवे/ SOUTH WESTERN RAILWAY

प्रेस विज्ञप्ति/ Press Release No. 338  Dt: 03.01.20201     

THE SUBWAY AT LONDA IS LIKELY TO ENTER IN LIMCA BOOK OF RECORDS FOR IT’S COMPLETION IN RECORD PERIOD OF 90 DAYS

Shri Ajay Kumar Singh, General Manager/South Western Railway conducted a trailing window inspection from Hubballi to Londa today.  He inspected the progress of doubling and electrification work between Hubballi and Londa. He was accompanied by Shri Vipul Kumar, Principal Chief Engineer;  Shri H.S. Verma, Principal Chief Operations Manager; Shri Arvind Malkhede, Divisional Railway Manager of Hubballi Division; Shri M.A.V. Ramanujam, Principal Chief Safety Officer; Shri P. Ravi Kumar, Principal Chief Mechanical Engineer,  Shri P.V. Rajasekhar, Principal Chief Signal and Telecommunication Engineer,  other PHODs and officers were present.

At Londa he has inspected recently constructed Limited Height Subway at Londa yard. This subway was constructed in just 90 days (right from the day of deciding that  the limited Height Subway to be constructed).  o­n 29th  September 2020, during the inspection of Londa yard, public of Gandhi Nagar represented to General Manager South Western Railway that they lacked road connection to main  Londa town and have to take detour of 3 Km to go to nearby level crossing gate to cross Railway track and Londa yard. Shri Singh instructed concerned officials to take up work of construction of Limited Height subway at this location as that is the most cost effective expeditiously  and quick solution to the problem being faced by 250 odd families.

Taking up the challenge, Hubballi Railway Division has completed the construction work within record time of 90 days. RUB underneath 5 running lines constructed in a record period of 90 days at Londa Railway Junction o­n Hubballi division. The cost of this subway is Rs. 6.12 Crores.  The activities completed in 90 days covers- work from Preparation of GAD/TAD, approvals, estimate preparation, processing for sanctions, and casting of 25 RCC Boxes and inserting these boxes, traffic block stretching over 36 Hours, construction of  wing- walls, approach roads, closure of LC by district authorities. Normally construction of any such sub way takes minimum 18-24 months.

For quickest possible completion, this Subway is likely to enter in Limca book of records.

Residents of Gandhi Nagar thanked South Western Railway headed by General Manager, South Western Railway profusely. They have expressed happiness as their nearly 70 year old requirement to have a grade separator is finally met and educational, agricultural  and  medical needs of residents of this area can be met.

Tree plantation has been done by Railway officials by the side of Limited Height subway.


                                                                   Chief Public Relations Officer                                                                    South Western Railway, Hubballi





  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.