Press Release No. 37104-02-2021
Hubballi
Press Release No. 371, DOUBLE LINE TRACK BETWEEN GUBBI-NITTUR (9 KM) PART OF ARSIKERE – TUMAKURU DOUBLING PROJECT COMPLETED

दक्षिण पश्चिम रेलवे/ SOUTH WESTERN RAILWAY

        प्रेस विज्ञप्ति/ Press Release No. 371  Dt: 02.02.2021                     

DOUBLE LINE TRACK BETWEEN GUBBI-NITTUR (9 KM) PART OF ARSIKERE – TUMAKURU DOUBLING PROJECT COMPLETED

Newly laid double line between Gubbi and Nittur Stations (9 Kms) o­n South Western Railway, Bengaluru Division was completed 1.2.2021.  This double line between Gubbi and Nittur Stations is part of the 96 Km doubling between Arsikere and Tumakuru.  65 Km have so far been commissioned in this section which includes Arsikere – Kardi (36 Km) in Nov 18, Kardi – Banasandra (11 Km) in Mar.20, Tumakuru – Gubbi (18 Km) in May 19.  Work is in progress in the section between Nittur – Banasandra and targeted to be completed by June 2021.


Arsikere – Tumakuru Doubling  was sanctioned in 2015-16 at a cost of Rs.783 Crs. (Revised)  Commissioner of Railway Safety (CRS)/ Southern Circle, Bengaluru completed statutory inspection of newly laid double line between Gubbi  and Nittur stations (9 Km)  o­n 30.12.2020  and after completion of all remaining works double line between has been opened to traffic from 01.02.2021.  Speed trial was conducted successfully at a Maximum speed of 126 kmph with NIL peaks.  Glass water challenge was also met with success during the trial.


Bengaluru-Hubballi line spanning 478 Km of which 400 Km is in Mysuru Division and the rest is in Bengaluru Division constitutes the main trunk route of SWR for Karnataka. Doubling of Railway track in this section will increase line capacity of this important line connecting Bengaluru to Hubballi, Belagavi, Mumbai etc., This will give impetus to rail infrastructure in the region of Arsikere – Tumakuru. The doubling project o­nce completed fully will result in much faster movement of trains and improve intercity connectivity.


Salient features of Gubbi-Nittur


Length of the section 9 Km

Cost of doubling section commissioned Rs.75.5 Cr.

Stations i. Gubbi

ii. Nittur

District covered Tumakuru

Parliamentary constituency Tumakuru

No of Minor bridges 15 Nos.

No of Major bridges 2 Nos.

No. of Road under bridges newly constructed Nil (one existing RUB extended)

No. of Road over Bridges (existing) 1 No.

No. of new Foot over bridges 2 Nos  (one commissioned & o­ne under construction).


Additional amenities provided @ Gubbi


Area of newly provided Platform shelter 224 Sqm

Length of newly constructed Platform Platform No.1 – 540m , Platform No.2 – 540m  High level

Foot Over Bridge 1 No

Toilets 2 Nos

Benches 25 Nos

Water booths 5 Nos

Trolley/path 2 Nos (at both ends)


Additional amenities provided @ Nittur


Area of newly provided Platform shelter 480 Sqm

Length of newly constructed Platform Platform No.2 – 480m HL

Foot Over Bridge 1 Nos (under construction)

Benches 25 Nos (under construction)

Water booths 5 Nos (under construction)

Trolley/path 2 Nos (at both ends)


The work of doubling of the section is monitored by Shri K C Swami, CAO/CN, and executed by Shri P R S Raman, CE/CN/East and Shri Shantiram, CSTE/CN and officers of Construction Organisation.


Shri Ashok Kumar Verma, Divisional Railway Manager of Bengaluru Division, with Branch officers of the division has ensured early commissioning of the section.


Shri Ajay Kumar Singh, GM/SWR said that infrastructure development was being given a thrust and doubling between Bengaluru and Hubballi was a priority for increasing line capacity and to enable SWR to run faster trains.


                                                                   Chief Public Relations Officer                                                                    South Western Railway, Hubballi





  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.