ENGINEERING DEPARTMENT

1.0TRACK STRUCTURE ON MAIN LINE

Route

Route Km

Running track km

Track structure with

PSC sleepers

60kg Rails

52kg (90UTS) Rails

52kg (72UTS) Rails

D

719.29

965.792

965.792

417.892

529

18.9

E

413.42

413.42

413.42

123.22

283.2

7

TOTAL

1132.71

1379.212

1379.212

541.112

812.2

25.9


1.1 LEVEL CROSSINGS

The details of level crossings as on 01.04.2020 over the Division is as under:

Manned

Un Manned

Grand Total

Total Manned

Engg

Traffic

Interlocked

Non Interlocked

279

234

45

120

159

0

279

 

2.0 LCSs ELIMINATED FOR LAST 3 YEARS

Sl.No

Description

2017-18

2018-19

2019-20

1

No of LCs eliminated

54

33

30

2.1 LIST OF LCs PLANNED FOR ELIMINATION BY CONSTRUCTION OF RUB (2020-21)

S.No.

Section

LC No.

Location

Between Station

Remarks

1

SPGR-UBL

135

273/700-800

NVF-AJP

Eliminated in Apr-2020

2

SPGR-UBL

139

230/500-600

AJP-SHV

 

3

SPGR-UBL

160

265/600-700

RGI-HLK

Eliminated in Oct-2020

4

SPGR-UBL

164

272/100-200

HLK-JRU

Eliminated in Jun-2020

5

JRU-RDG

43

66/800-900

BAHI-CHKE

Eliminated in July-2020

6

MYS-ASK

21

25/900-26/000

STE-KRNR

Eliminated in July-2020

7

MYS-ASK

23

27/900-28/000

STE-KRNR

Eliminated in July-2020

8

MYS-ASK

28

32/900-33/000

STE-KRNR

 

9

MYS-ASK

66

71/300-400

MGF-HLN

 

10

MYS-ASK

67

73/00-100

MGF-HLN

 

11

HAS-MAJN

47

47/400-500

SKLR-DOGL

 

12

HAS-MAJN

48

47/600-700

SKLR-DOGL

 

13

SPGR-UBL

106

175/800-900

ASK-BVR

 

14

RRB-SMET

19

25/900-26/000

TKE-MSS

 

15

RRB-SMET

44

58/800-900

BDVT-SMET

 

16

SMET-TLGP

93

133/600-700

ANF-SRF

 

17

RRB-TLGP

68

81/500-600

SMET-KMSI

Eliminated in June-2020

18

JRU-RDG

3

5/500-600

JRU-AMC

Eliminated in Oct-2020

19

HRR-UBL

221

369/800-900

DAD-BYD

Eliminated in Aug-2020



2.2 ROB/RUB ARE BEING EXECUTED BY CN ORGANISATION IN LIEU OF LCs

Sl.No

Section

LC

Location

Between Station

1

SPGR-ASK

66

113/200-300

SPGR-AMSA

2

SPGR-ASK

84

139/900-140/000

RDI-TTR

3

SPGR-ASK

86

142/700-800

TTR-HVL

4

ASK-HRR

184

299/000-100

MYK-KAG

5

ASK-HRR

199

324/700-800

THN-DVG

6

ASK-HRR

208

337/100-200

AVC-HRR

7

HRR-UBL

217

359/500-600

CLI-RNR

8

HRR-UBL

218

362/100-200

RNR-DAD

9

HRR-UBL

224

375//800-900

DAD-BYD

10

HRR-UBL

227

380/300-400

BYD-HVR

11

HRR-UBL

236

391/200-300

BYD-HVR

12

MYS-ASK

5

4/700-800

MYS-BLGA

13

MYS-ASK

7

6/600-700

MYS-BLGA

14

MYS-ASK

31

38/000-100

KRNR-HAH

15

MYS-ASK

51

57/000-100

AKK-MGF

16

MYS-ASK

78

87/800-900

HLN-MVC

17

MYS-ASK

79

88/200-300

HLN-MVC

18

MYS-ASK

112

133/300-400

HAS-BGPA

19

HAS-SKLR

3

1/600-700

HAS-ALUR

20

JRU-RDG

1

1/100-200

JRU-AMC

21

JRU-RDG

15

25/400-500

AMC-CTA

22

JRU-RDG

22

33/700-800

CTA-BAHI

23

RRB-SMET

34

47/400-500

BDVT-SMET

24

SMET-TLGP

49

63/900-64/000

SMET-KMSI

25

SMET-TLGP

52

66/200-300

SMET-KMSI

26

MYS-CMNR

1

1/400-500

MYS-AP

27

MYS-CMNR

37

41/700-800

NTW-CMNR


 


          3.0 STATUS OF INCREASING OF SECTIONAL SPEED (2020-21)

Sl.No

Section

Length
Km

Exg Speed

Pro Speed

Speed increased W.E.F

Remarks

1

DRU-CMGR

45.00

60

100

15.06.2020

 

2

AVC-KTY

60.30

60

90

01.10.2020

 

3

RRB-JRU

136.58

100

110

05.11.2020

 

4

SPGR-ASK

110.00

ASK-RDI = 100
RDI-SPGR = 95

110

-

Speed trial conducted on 05.10.2020. Proposal submitted to CRS on 17.11.2020 BY Hq.

 

3.1 Status of Increasing Speed on Loop Lines & Turn Outs from 15 kmph to 30kmph ( 2020-21)

Sl.No

Section

KM

Length

No Of Station

No of Loop lines

Remarks

1

RRB-TLGP

0.00-159.83

160

8

12

Proposal submitted to Hqrs on 26.05.2020. Sped trial to be conducted

2

MYS Yard

-

-

-

3

CRS remarks recd on 13.01.20.Compliance of the same( S & T) forwarded CRS on 13.07.2020 by Hqrs

3

THN Yard

-

-

-

1

Speed increased w.e.f 26.05.2020

4

MYS-CMNR

0.0-60

60

4

6

Proposal submitted to HQ ON 24.07.2020. Speed trial conducted and report of the same submitted to HQ on 14.10.2020

 

4.0 RAIL / WELD FAILURES:

Description

2018-19

2019-20

2020-21

RF

WF

RF

WF

RF

WF

Division

61

15

64

9

22

0

 

5.0 TARGET OF KEY ACTIVITIES AND PROGRESS IN THE LAST 3 YEARS

S.No

Activity

2017-18

2018-19

2019-20

Target

Actuals

Target

Actuals

Target

Actuals

1

TRR (P) (KM)

57.88

52.89

97.31

17.82

70

41.91

2

TSR (P) (KM)

26.85

19.7

27.89

13.21

25

22.95

3

TRR (S)

3.58

3.65

7.5

1.85

10

4.87

4

TSR (S) (KM)

4.25

4.9

0

0

0

0

5

TTR (CS+CMS) (KM)

21

5

16

14

2

20

6

TTR (CS)

0

52

0

41.5

0

0

7

TTR(CMS)

19

59

30

38

2

0

8

TWR

38

28.38

43.62

28.6

50

22.55

9

Ballast collection (cum)

125

140.221

155

183.35

255

226

10

Ballast Insertion (cum)

125

131.916

155

155.77

255

287

11

Deep Sereening plain track(KM)

63

55.34

115

94.87

150

142.35

12

Machine

 80

45.58

80

86.49

120

130.96

13

Manual

 30

11.75

35

8.39

30

11.39

14

Deep screening of Turn outs

36

65

75

77

120

106

15

Shallow screening

64

81.91

130

130.31

200

113.33

16

Scrap

3000

4174.46

8550

3566.23

7000

5439.33

17

Removal of PSR

27

26

21

19

6

5


6.0       VACANCY POSITION IN SAFETY CATEGORY

SN

Category

Sanctioned strength

Actuals

Vacancy

1

SSE/P.way

79

49

30

3

JE/P.way

42

33

9

5

Track Maintener  Gr.I, II, III & IV

2410

2366

526

 

 

7.0  DOUBLING WORK BEING EXECUTED BY CN UNIT

Sl.No

Between Station

TDC

1

HRR-DAD

30.11.2020

2

THN-DVG

31.03.2021

3

AMSA-BSN

31.03.2021

 

  8.0 MONSOON PREPAREDNESS OF THE DIVISION

(i) Monsoon booklet prepared and monsoon reserve as per yardstick

(ii) Loading of monsoon reserve in wagons: Allotment of wagons requested by CBE at HQ. Loading of monsoon materials are completed.

(iii) In SKLR-SBHR ghat section, Agencyfixed for clearing of likely earth slips during monsoon.

 

 ---




Source : South Western Railway CMS Team Last Reviewed on: 23-11-2020  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.