PROGRESS OF WORKS FOR THE MONTH OF
APRIL 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2023 | BG 2023-24 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NL PB-3 | Hassan-Bangalore New BG via Shravanabelagola (167 km) | 1996-97 | 1736.60 on 50:50 cost sharing basis between Rly and Gok | 1763 | 33 Cr (Cap.) 0 Cr (Deposit) | 0.10/ 1763.10 | 100% |
Remarks:-
Project completed and commissioned in 2017.