PROGRESS OF WORKS FOR THE MONTH OF
FEBRUARY 2023
Cate-gory | Details of Work | Year of sanction | | Cum. Exp. Up to March 2022 | BG 2022-23 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-6 | Rayadurga-Tumkur(207Km)(12 Block sections) | 2007-08 | 2404.03 on 50:50 cost sharing basis between Rly and Gok / GoAP | 1098.72 | 50 Cr(Cap.)
50 Cr(Dep.) | 115.53/ 1214.25 | 58% |
Remarks:- Section from Rayadurga-Kalyanadurga-Kadiridevarapalli (63 km) which falls in A.P. was commissioned in 2016-17.
Section between Kadiridevarapalli - Doddahalli (20 km) is has been commissioned on 15.02.2023.
The work for the remaining sections is planned to be taken up under Engineering Procurement & Construction mode of tendering after handing over of 90 % of land by Government of Karnataka. EPC Tender called for section between Tumkur-Koratagere (30 km) for a value of Rs.270.31 Cr on 16.11.2022 and is due for opening on 17.04.2023.
|