Rayadurga-Tumkur

PROGRESS OF WORKS FOR THE MONTH OF
FEBRUARY 2023

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2022

BG

2022-23

Exp. Up to the month/ Cum. Exp.

Physical progress

NLPB-6

Rayadurga-Tumkur(207Km)(12 Block sections)

2007-08

2404.03

on 50:50 cost sharing basis between Rly and Gok / GoAP

1098.72

50 Cr(Cap.)


50 Cr(Dep.)

 

115.53/ 1214.25

58%

Remarks:-

 

Section from Rayadurga-Kalyanadurga-Kadiridevarapalli (63 km) which falls in A.P. was commissioned in 2016-17. 


  Section between Kadiridevarapalli - Doddahalli (20 km) is has been commissioned on 15.02.2023.


    The work for the remaining sections is planned to be taken up under Engineering Procurement & Construction mode of tendering after handing over of 90 % of land by Government of Karnataka. 

   

    EPC Tender called for section between Tumkur-Koratagere (30 km) for a value of Rs.270.31 Cr on 16.11.2022 and is due for opening on 17.04.2023.





 




Source : South Western Railway CMS Team Last Reviewed : 28-03-2023  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.