PROGRESS OF WORKS FOR THE MONTH OF
July 2020

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2020

RG for 2020-21

Exp. Up to the month/ Cum. Exp.

Physical progress

NLPB-3 SC Rly

Munirabad

(Ginigera)-Raichur(165 km)

2007-08

1350.91

Cost sharing on 50: 50 basis between GoK &Rly.

1148.78

60.00

90.61/ 1284.41

40%

Remarks:-

 

   Section between Ginigera-Chikkabenakal (27 km) commissioned on 31.03.2017 for passenger traffic.  

Chikkabenakal (Km 27)-Gangavathi (Km 40) – 13 km commissioned on 04.03.2019.

Gangavathi (km 40)-Karatagi (Km 68)-Sidhanur (km 84) - CRS inspection done on 30.05.2020 and authorization received.





Source : South Western Railway CMS Team Last Reviewed on: 19-08-2020  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.