PROGRESS OF WORKS FOR THE MONTH OF
JANUARY 2023
Cate-gory | Details of Work | Year of sanction | | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-8 | Tumkur- Chitradurga-Davangere (199.7 km) | | 2000.97/1801.01 On 50:50 cost sharing basis & land free of cost | 85.74 | 50.00 Cr.(Cap.) | 21.05/ 106.79 | 6 |
Remarks:- - Section Tumkur - Urukere (11.5 km) is a part of Tumkur - Rayadurg New line Project
- Urukere - Thimmarajanahalli (18.3 km) - Work in progress.
- LOA issued for EPC Contract for work between Tolahunse - Bharmasagara (20.36 km) and work is in progress.
- The work in balance sections are planned to be executed phase wise through EPC mode of tendering after handing over of 90% of land.
|