PROGRESS OF WORKS FOR THE MONTH OF
July 2020
Cate-gory | Details of Work | | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2020 | BG for 2020-21 | Exp. Up to the month/ Cum. exp | Physical progress |
NL PB-11 | Marikuppam – Kuppam ( 23.70 Km) | | 279.54 | 32.19 | 0.00 | 0.73 / 32.92 | Nil |
Remarks: Work could not be commenced till date due to non- availability of land. land for first 6 km is falling in Karnataka State from Marikuppam end. Now High Court of Karnataka has given permission for acquisition of BGML land subject to deposition of requisite cost of land in Court. The entire amount of Rs.2.78 cr. has been deposited with Hon’ble High Court. Land is yet to be handed over by BGML and GoK for stretch in Karnataka State. Land acquisition is in process by A.P. Govt. for stretch falls in A.P. Amount about Rs.18 cr. has been deposited on 11.01.19 with DC/Chittoor for land in Andhra Pradesh state. Railway has been allowed to commence the work by BGML. Accordingly, physical works have been commenced.
|