PROGRESS OF WORKS FOR THE MONTH OF
July 2020
Cate-gory | Details of Work | | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2020 | BG for 2020-21 | Exp. Up to the month/ Cum. exp | Physical progress |
NL PB-12 | Chikballapur-Puttaparthy-Sri Satya Sai Nilayam (103 km) | | 692.43 On 50:50 cost sharing basis & land free of cost | 0.00 | 0.10 | 0.00/ 0.00 | Nil |
Remarks:- CCEA clearance awaited. |