PROGRESS OF WORKS FOR THE MONTH OF
JANUARY 2023
Cate-gory | Details of Work | Year of sanction | | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-7 | Bagalkot-Kudachi(142 kms) | 2010-11 | 1654.65/1378 on 50:50 cost sharing basis & land free of cost by GOK | 326.63 | 25.00 (Cap.) 25.00 (Deposit) | 9.46/ 336.09 | 30% |
The section between Bagalkot - Kajjidhoni (30 Km) was commissioned on 21.06.2018.
For the section between Kajjidoni - Lokapur (7 Km) - Work is in progress and is targeted to be commissioned in the Financial year 2023-24.
Engineering Procurement and Construction (EPC) Tender called for section between Lokapur - Yadwad (21 Km) on 15.11.2022 for a value of Rs.357.45 Cr and is due for opening on 20.02.2023.
From Yadwad to Kudachi land is yet to be handed over to the Railways from Government of Karnataka. After handing over of 90% of land EPC tenders will be called in stages. |