on 50:50 cost sharing basis and land free of cost
0.89
50.00(Cap.)
1.65/2.54
Nil
Remarks:-
Execution of the project is planned in 2 phases, Shimoga to Shikaripura (46 Km) under phase I and balance under phase II. NIT (EPC mode of tendering) has been published during July for the new line section between Koteganguru & Shikaripura (39.38 km) at a value of Rs. 517.73 Cr. The work for the balance section is also planned to be executed through EPC mode of tendering.
Source : South Western Railway CMS Team Last Reviewed : 12-01-2023