Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2020

B for 2020-21

Exp. Up to the month/ Cum. exp

Physical progress

DL

PB-36

 

Yelahanka-Penukonda

(120.55 km)

2015-16

988.37

822.49

155.00

33.68/  856.17

25%

Remarks:-

1. A portion of this project, i.e. 48.2 km falls in A.P. out of total length of 120.53 km.

2.  Makalidurga-Devarapalli (36 km) commissioned on 05.04.2019.  Work is in progress between Yelahanka-Doddaballapur-Makalidurga (36 km).




Source : South Western Railway CMS Team Last Reviewed on: 19-08-2020  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.