PROGRESS OF WORKS FOR THE MONTH OF
FEBRUARY 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. exp | Physical progress |
DL PB-30 | Arsikere-Tumkur(96 km) | 2015-16 | 758.36/749.69 | 677.17 | 5.00 Cr (Cap.) 46.80 Cr (EBR(IF)/IRFC) | 37.12/ 714.29 | 100% |
| | | | | | | | |
Remarks:-
Entire Arsikere - Tumkur Doubling was completed and commissioned on 25.02.2022 and dedicated to the nation by Hon’ble PM on 20.06.2022.