Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2020

BG for 2020-21

Exp. Up to the month/ Cum. exp

Physical progress

DL PB-27 of C.Rly.

Miraj-Londa (185.90 km)

2015-16

1190.90

439.03

245.00

55.24/ 492.27

 10%

Remarks:-


This project is part of Pune-Miraj-Londa Doubling (467 km) sanctioned under Pink Book of Central Railway.  Works are in progress.   CRS inspection between Ghataprabha-Chikkodi (15 km) done on 16.10.2019 and section commissioned on 11.12.2019.




Source : South Western Railway CMS Team Last Reviewed on: 19-08-2020  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.