ROAD UNDER BRIDGEs PERTAINING TO CONSTRUCTION UNIT/SWR AS PER PINK BOOK 2023-24 |
SN | Name of the work |
RUB commissioned: 1 No. |
1 | Yesvantpur- Yelahanka-RUB in lieu of LC No.5. ( At Mathikere) |
Work in progress: 2 Nos. |
1 | UBL-LD section - Construction of RUB of 2x9.25x5.50m with RCC boxes in lieu of LC No 300 at km 492/500-600 on UBL-Haliyal road |
2 | Construction of RUB 299 at km 491/400-500 on UBL-LD section on cost sharing basis |
ESTIMATE YET TO BE SANCTIONED: 3 Nos. |
1 | Mysuru- Chamarajanagar- RUB in lieu of LC No.1 (Near Mysuru) |
2 | RUB in lieu of LC No. 51 (Between Akkihebbalu-Mandagere) |
3 | RUB in lieu of LC No.199A at Davanagere.(2X7.5X4.5) |
Drawing under preparation/Approval: 2 Nos. |
1 | Mysuru-Arsikere -RUB in lieu of LC No. 5 (Near Mysuru) |
2 | Londa-Miraj - RUB in lieu of LC No.380 at railway Km. 606/900-607/000 of Desur-Belagavi stations. |