रामनगरम-मैसूरु

Sl. No

Cate-gory

Details of Work

Year of sanction

Original sanctioned Pink Book cost

Latest Anticipated /Sanctioned Cost

Cum.Exp. Up to  31.03.17

Physical progress

2

DL     PB-26

Ramanagaram-Mysore doubling (93km) with electrification of Kengeri-Mysore (125 km)

2007-08

363.18

874.57

962.25

91%

ØEntire doubling between Ramanagaram-Mysore (92.50 km) has been completed and commissioned . Tippu Sultan Armoury has been successfully shifted to revised location and civil works in 1.5 km section started and targetted to be commissioned by July 2017. Both North and South Cauvery bridges have been completed.


Electrification from Kengeri to Mysore (125 km):-

Status:-

OHE work between Kengeri to Yeliyur has been completed.CRS inspection from Kengeri to Ramanagaram done on 23.08.2016 and section commissioned.CRS inspection from Ramanagaram to Yeliyur also done on 05.04.2017.The work in the remaining section is also under progress.







Source : दक्षिण पश्चिम रेलवे CMS Team Last Reviewed : 26-07-2023  


  प्रशासनिक लॉगिन | साईट मैप | हमसे संपर्क करें | आरटीआई | अस्वीकरण | नियम एवं शर्तें | गोपनीयता नीति Valid CSS! Valid XHTML 1.0 Strict

© 2010  सभी अधिकार सुरक्षित

यह भारतीय रेल के पोर्टल, एक के लिए एक एकल खिड़की सूचना और सेवाओं के लिए उपयोग की जा रही विभिन्न भारतीय रेल संस्थाओं द्वारा प्रदान के उद्देश्य से विकसित की है. इस पोर्टल में सामग्री विभिन्न भारतीय रेल संस्थाओं और विभागों क्रिस, रेल मंत्रालय, भारत सरकार द्वारा बनाए रखा का एक सहयोगात्मक प्रयास का परिणाम है.