Sl. No | Cate-gory | Details of Work | Year of sanction | | | Cum.Exp. Up to 31.03.17 | Physical progress |
2 | DL PB-26 | Ramanagaram-Mysore doubling (93km) with electrification of Kengeri-Mysore (125 km) | 2007-08 | 363.18 | 874.57 | 962.25 | 91% |
ØEntire doubling between Ramanagaram-Mysore (92.50 km) has been completed and commissioned . Tippu Sultan Armoury has been successfully shifted to revised location and civil works in 1.5 km section started and targetted to be commissioned by July 2017. Both North and South Cauvery bridges have been completed.
Electrification from Kengeri to Mysore (125 km):-
Status:-
OHE work between Kengeri to Yeliyur has been completed.CRS inspection from Kengeri to Ramanagaram done on 23.08.2016 and section commissioned.CRS inspection from Ramanagaram to Yeliyur also done on 05.04.2017.The work in the remaining section is also under progress.