Achievements


1) PROVISION OF 6 Nos ESCALATORS OVER SBC DIVISION

6 Nos Escalators - 5 Nos at KSR SBC Station & 1 Nos at YPR Station were installed, tested & commissioned within record time of 6 months. SBC Division was the first Division in Indian Railway to complete the entire project sanctioned under the PB Work.