Munirabad-(Ginigera)-Raichur

PROGRESS OF WORKS FOR THE MONTH OF
September 2022

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2022

RE projected 2022-23

Exp. Up to the month/ Cum. Exp.

Physical progress

NLPB-3 SC Rly

Munirabad

(Ginigera)-Raichur(165 km)

2007-08

2599.67

Cost sharing on 50: 50 basis between GoK &Rly.

1423.00

300.00

84.97/ 1507.97

55%

Remarks:-

 

   Section between Ginigera-Chikkabenakal (27 km) commissioned on 31.03.2017 for passenger traffic.  

Chikkabenakal - Gangavathi – 13 km commissioned on 04.03.2019. Gangavathi - Karatagi (26 km) commissioned on 31.05.2022.

The section between Karatagi - Sindhanur (18.5 km) is targeted to be commissioned in the current financial year 2022-23.

The work in the balance section is planned to be taken up under Engineering Procurement & Construction mode of tendering after handing over of 90% land by Government of Karnataka.





Source : South Western Railway CMS Team Last Reviewed : 17-10-2022  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.