PROGRESS OF WORKS FOR THE MONTH OF
APRIL 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2023 | BG 2023-24 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-3 SC Rly | Munirabad (Ginigera)-Raichur (165 km) | 2007-08 | 2599.67/1350.91 Cost sharing on 50: 50 basis between GoK &Rly. | 1731.50 Cr | 150 Cr (Cap.) 150 Cr (Deposit) | 69.88/ 1801.38 | 60% |
The sections between Ginigera - Chikkabenakal (27 km) commissioned on 31.03.2017, Chikkabenakal - Gangavathi (13 km) commissioned on 04.03.2019 & Gangavathi - Karatagi (26 km) commissioned on 31.05.2022.
The section between Karatagi - Sindhanur (18.5 km) is targeted to be commissioned in July 2023.
Engineering Procurement & Construction (EPC) Tender called for section between Sindhanur – Hirekotengal (30 Km) on 22.03.2023 and is opening on 19.07.2023.
The work in the balance section is planned to be taken up under Engineering Procurement & Construction mode of tendering after handing over of 90% land by Government of Karnataka.