PROGRESS OF WORKS FOR THE MONTH OF
DECEMBER 2022
Cate-gory | Details of Work | Year of sanc-tion | | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NL PB-2 | Kadur-Chikmagalur-Sakleshpur (93kms) | 1996-97 | 826.18/534.88 On 50:50 cost sharing basis to Kadur-Chikmagalur (46km) & Chikmagalur – Sakleshpur (47 km) land free of cost and balance cost on 50:50 basis between Gok & Rly. | 496.05 | 41.00(Cap.) 68.00(Deposit) | 3.10 / 499.16 | 61% |
Remarks:- ØSection from Kadur to Chikmagalur (46 km) was completed and commissioned on 19.11.2013. ØWorks between Chikmagalur – Sakleshpur were frozen by Railway Board since 2007 and defreezed during 2013.However, GoK vide G.O. No.IDD 95 NSW 2018 dated 17.01.2019 has advised that the section between Belur-Sakleshpur line stretch in Chikmagalur-Belur-Sakleshpura railway line to be dropped and to take up Belur-Hassan new railway line for which separate sanction from Railway Board dated 01.03.2019 has been received. Railway Board vide letter dated 07.06.19 conveyed approval to freeze works on Belur-Sakleshpur in view of sanction of Hassan(Alur)-Belur NL project. Accordingly, work will be taken up in Chikmagalur-Belur (22 km) only. - Chikmagalur - Belur(22 km) - Planned to be executed in two phases:
- Chikmagalur - Hadihalli (9 km) - Engineering Procurement & Construction (EPC) Tender floated on 20.8.22 as more than 95% of land is available.
- Hadihalli - Belur (13 km) - Tender will be called .139.48 acres of land for Hadihalli-Belur section is yet to be handed over.
|