PROGRESS OF WORKS FOR THE MONTH OF
DECEMBER 2022
Cate-gory | Details of Work | Year of sanction | | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-4 | Hubli-Ankola (167 kms) | 1996-97 | 5174.30/103.73 | 158.13 | 0.0001 | 1.31/ 159.44 | 10% |
Remarks:- Earthwork and bridge works upto 34.8 km from Hubli end to Kiravatti completed. Further work stopped by MoEF & CEC during 2006 due to environmental issues. No work has been carried out since 2006 till date as per the order of CEC for want of MoEF clearance. The matter is sub-judice.
|