PROGRESS OF WORKS FOR THE MONTH OF
APRIL 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2023 | BG for 2023-24 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-8 | Tumkur- Chitradurga-Davangere (199.7 km) | 2011-12 | 2000.97/1801.01 On 50:50 cost sharing basis & land free of cost | 107.15 Cr | 220.85 (SF.) Cr. 200.(Dep.) | 1.42/ 108.57 | 6 |
Remarks:-
Section Tumkur - Urukere (11.5 km) is a part of Tumkur - Rayadurg New line Project.
Urukere - Thimmarajanahalli (13.5 km) - Work in progress.
LOA issued for Engineering Procurement & Construction (EPC) Contract for work between Tolahunse - Bharmasagara (20.36 km) and work is in progress.
The work in balance sections are also planned to be executed phase wise through Engineering Procurement & Construction (EPC) mode of tendering after handing over of 90% of land by Government of Karnataka.