PROGRESS OF WORKS FOR THE MONTH OF
JANUARY 2023
Cate-gory | Details of Work | | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. exp | Physical progress |
NL PB-13 | Gadag-Wadi (257 km) | | 2841.84 with cost sharing basis & land free of cost by GOK | 455.83 | 75 Cr.(Cap.) 112 Cr. (Deposit) | 82.85/538.68 | 22 |
Remarks:- The section between Talkal - Sangnal (22 kms) has been commissioned in March 2022. The section between Sangnal - Linganbandi (23.7 km) is targeted to be commissioned in the current Financial Year 2022-23 and the section between Linganbandi - Kushtagi (10 km) is targeted to be commissioned in 2023-24. The work for the balance sections is planned to be taken up in phases through EPC mode of tendering after handing over of 90% of land by Government of Karnataka.
|