Shimoga-Shikaripura-Ranibennur (89 km)

             PROGRESS OF WORKS FOR THE MONTH OF
                                  September 2022

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2022

BG for 2022-23

Exp. Up to the month/ Cum. exp

Physical progress

NL

PB-176

Shimoga-Shikaripura-Ranibennur NL (89 km)

2019-20

994.47  

  o­n 50:50 cost sharing basis and land free of cost

0.89

50.00

1.09/1.99

Nil

Remarks:-    

Execution of the project is planned in 2 phases, Shimoga to Shikaripura (46 Km) under phase I and balance under phase II. NIT (EPC mode of tendering) has been published during July for the new line section between Koteganguru & Shikaripura (39.38 km) at a value of Rs. 517.73 Cr. The work for the balance section is also planned to be executed through EPC mode of tendering.





Source : South Western Railway CMS Team Last Reviewed : 17-10-2022  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.