Ramanagaram - Mysore doubling (94km) with electrification of Kengeri-Mysore
2007-08
1200/874.57
50:50
(Rly:GoK)
1143.62
20.00
(EBR(IF)/IRFC)
31.87/1175.49
95%
Remarks:-
Entire doubling between Ramanagaram-Mysore (94 km) along with electrification has been completed and commissioned in Nov.2017. With this the entire doubling work between Bangalore to Mysore has been completed and commissioned. The electrification between Bangalore - Mysore was dedicated to the Nation by Hon'ble Prime Minister on 19.02.2018 at Mysore.
Source : South Western Railway CMS Team Last Reviewed : 12-01-2023