Remarks:- Doubling for part length of this project, i.e. from Hotgi-Kudgi (134 km) is taken up under Customer Funding Model. The section between Gadag to Kudgi(150 Km) is taken up as an EBR(IF) funded project. So far, Wandal - Hotgi (148 Km - NTPC Portion), Gadag - Hole Alur (52 Km) and HoleAlur-Badami(19 Km) has been commissioned between 2018 - 2022 . The section between Badami-Guledagudda(12 Km) is targeted to be commissioned in the current financial year 2022-23. The balance section Guledagudda - Wandal(53 Km) is targeted to be commissioned in March 2024. |