Cate-gory | Details of Work | | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. exp | Physical progress | DL PB-29 | Hubli-Chikjajur (190 km) | | 1849.50/1156.94 100% Rly funded | 1338.12 | 10.00 | 143.19/ 1481.31 | 85% | Remarks :- Sections between Chikjajur-Devaragudda, Haveri - Saunshi & Hubli - Hubli South (Total 145 km) has been commissioned in phases during 2018 - 2022. Balance sections Hubli South - Saunshi (20 Km) & Devaragudda - Haveri (25 Km) are targeted to be commissioned in the current financial year 2022-23. With this the entire project will be commissioned in 2022-23.
|
Source : South Western Railway CMS Team Last Reviewed : 12-01-2023
|
|
|