PROGRESS OF WORKS FOR THE MONTH OF
FEBRUARY 2023
Cate-gory | Details of Work | Year of sanction | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2022 | BG for 2022-23 | Exp. Up to the month/ Cum. exp | Physical progress |
DLPB-35# | Hosur - Omalur DL (147 Km) | | 1470 | 0.00 | 1.00 (EBR(IF)/IRFC) | 0.00/ 0.00 | Nil |
| | | | | | | | |
Remarks:-
Final Location Survey completed. DPR is under submission to Railway Board.