Cost sharing works (CS) : Projects shared between State Govt and Railways Accommodation works (AW): Crossing works like Road over bridge, Road under bridge & Subways pertaining to already sanctioned Doubling/New line projects Deposit works: Projects/works done by Railway for other Govt bodies/Private parties
|
SN | Type of work (CS/AW) | Description of work ( LC No, between stations & section ) | Month & year of commission |
2010-11 |
1 | CS | ROB in lieu of LC no. 132 at Km:332/600-700 between Krishnarajapuram-Whitefield stations in Jolarpet-Bengaluru section | April-2010. |
2 | CS | ROB in lieu of LC no. 53 at Km: 57/600-700 between Nanjangud-chamrajanagar stations in Mysuru-chamrajnagar section | May-2010. |
3 | CS | ROB in lieu of LC no. 32 at Km:45/500-600 between Bhadravati-Sivamogga stations in Birur-Talaguppa section | March-2011. |
2013-14 |
1 | CS | ROB in lieu of LC no. 40 & 41 at Km:72/500-600 between Tumakuru- Mallasandra stations in Tumakuru-Arsikere section | April-2013. |
2014-15 |
1 | Cs | ROB in lieu of LC no. 33 at Km:45/700-800 between Bhadravati-Sivamogga stations in Birur-Talaguppa section | April-2014. |
2 | CS | Bangalore -Mysore RUB in lieu of LC No. 4 at KM 3/800-900(NYH) (RPC layout) | Jan-15' |
3 | AW | RUB in Lieu of LC No.52 between Channapatna-settihalli stations in Ramanagaram-Mysuru section. | May'14 |
4 | AW | RUB in lieu of LC 58 between Settihalli-Maddur stations in Ramanagaram-Mysuru section. | May'14 |
5 | AW | RUB in lieu of LC No 140 between Ajjampura-Shivani stations in Birur-Chikjajur section | Dec'14 |
6 | AW | RUB in lieu of LC No 149 between Shivani-Hosadurga Road stations in Birur-Chikjajur section. | March'15 |
7 | AW | subway in lieu of LC NO. 157 @ Ch . 259812 between Ramagiri-Holakere stations in Birur-Chikjajur section | March'15 |
8 | AW | subway in lieu of LC NO. 158 @ Ch . 262621between Ramagiri-Holakere stations in Birur-Chikjajur section | March'15 |
9 | AW | subway in lieu of LC NO. 163 @ Ch . 270487 between Ramagiri-Holakere stations in Birur-Chikjajur section | March'15 |
10 | AW | subway in lieu of LC NO. 165 @ Ch . 272856 between Ramagiri-Holakere stations in Birur-Chikjajur section. | March'15 |
11 | AW | subway in lieu of LC NO. 166 @ Ch . 275132.20 between Ramagiri-Holakere stations in Birur-Chikjajur section. | March'15 |
12 | AW | subway in lieu of LC NO. 167 @ Ch . 259812 between Chikjajur-Sasalu stations in Birur-Chikjajur section. | March'15 |
2015-16 |
1 | CS | Yeshvantpur -Yelahanka - ROB in lieu of LC no. 11 between Yeshvantpur -Yelahanka stations in Yeshvantpur -Yelahanka section | Jan-2016' |
2 | CS | ROB in lieu of LC No:198 between Davanagere-Tolahunse stations in Chikjajur-Hubballi section. | Jan/16 |
3 | CS | RUB in lieu of LC No.64 between Koppal – Ginigera stations in Hosapete-Hubballi section | Mar/16 |
4 | CS | RUB at LC No. 10 A between YPR and YNK stations in Yesvantpur -Yelahanka section | Mar/16 |
5 | CS | ROB in lieu of LC No. 95 A between Pandavapaura- Byadarahalli stations inj Bengaluru-Mysuru section. | Nov--2015' |
6 | CS | RUB in lieu of LC No 101 between Srirangapattana - Naganahally stations in Bengaluru-Mysuru section. | Nov-2015. |
7 | AW | LHS in lieu of LC No 145 at Km 239/200-300 between Shivani-Hosadurga road stations . in Arsikere Harihar section | August'15 |
8 | Deposit | RUB in lieu of LC no:40 between Tumakuru-Mallasandra stations.(deposit work for TUDA of GOK) in Tumakuru- arsikere section. | Mar/16 |
9 | Deposit | ROB in lieu of LC No. 113 between nagasamudram and Dharavaram stations in Baiyyappanahalli-Dharmavaram section | Feb/16 |
2016-17 |
1 | CS | ROB in lieu of LC no. 4 & 4-B at Km 7/500-600 near Jalahalli between Yesvantpur-chikbanavara stations in Bengalru- Tumakuru section. ( LC no.4 ) | Jan-2017. |
2 | CS | ROB in lieu of LC no. 4 & 4-B at Km 7/500-600 near Jalahalli between Yesvantpur-chikbanavara stations in Bengalru- Tumakuru section.( LC no. 4- B ) | Jan-2017. |
3 | CS | ROB in lieu of LC no. 114 Between Bellari-Bellari cantonemnent stations in Hosapete-Ballari section. | Feb-2017. |
4 | CS | ROB in lieu of LC No.385 at Belgavi station between Belagavi -Sambre stations in Londa-Miraj section | Oct-16' |
5 | AW | ROB in lieu of LCNo. 156 between Hosadurga road -Ramagiri stations in Arsikere-Chikjajuru section | Sep/16 |
6 | AW | ROB in lieuof LC No. 169 between Chikjajur-Sasalu stations in Chikjajur-Hubballi section. | Oct/16 |
7 | AW | RUB in lieu of LC No.168 between Chikjajur-Sasalu stations in Chikjajur-Hubballi section. | Sept. 2016 |
8 | CS | ROB in lieu of LC No:131 between Baiiyyappanahalli-Carmelram in YPR-Salem section | March-17' |
2017-18 |
1 | CS | ROB in lieu of LC No.388-A. at Belgavi station between Belagavi -Sambre stations in Londa-Miraj section | March 2018 . |
2 | CS | ROB in lieu of LC No.32 between Doddaballapur - Oddarahalli stations in Baiyyappanahalli-Dharmavaram section. | JAN 2018. |
3 | CS | ROB in lieu of LC No.112 between Bellari Cant- Bellari Junction stations in Hosapete-Bellari section. | Nov-2017. |
4 | CS | ROB in lieu of LC No.1 between Hubballi - Kusugal stations in Hubballi- Hosapete section. | Sep-2017 |
5 | CS | ROB in lieu of LC no:4-A with subway between Yesvantpur- Yelahanka stations between Yesvantpur-Yelahanka section | JUNE 2017. |
6 | CS | ROB in lieu of LC No:21 between Yelahanka-Rajankunti stations in Baiyyappanahalli-Dharmavaram section. | Aug-2017.
|
7 | AW | ROB in lieu of LCNo. 176 between Mayakonda-Sasalu stations Chickjajur-Hubli section. | Feb-2018.
|
8 | AW | ROB in lieu of LCNo. 213 at Chalgeri yard between Ranebennur-Chalgeri stations in Chickjajur-Hubli section. | Feb-2018.
|
2018-19 |
1 | CS | -ROB in lieu of LC No.27 between Rajanukunti-Doddaballapura stations in Baiyyappanahalli-Dharmavaram section | August -2018 |
2 | CS | ROB in lieu of LC No.89 Between Mavinakere-Holenarsipur stations in Hassan Mysuru Section | Dec-18' |
3 | CS | ROB in lieu of LC No.62 between Banapur -koppala stations ( at Koppala yard)in Hubballi-Hosapete Section | 4 th March-19' |
4 | CS | ROB in lieu of LC No.116 between Bangarpet - Maralahalli stations in Bengaluru-Jolarpet section. | March-19' |
5 | CS | RUB in lieu of LC No.10 between Yesvantpur- Yelahanka stations in Yesvantpur- Yelahanka section | March-19' |
6 | CS | RUB in lieu of LC No:131 between whitefield -Krishnarajapuram stations in Bengaluru-Jolarpet section | March-19' |
7 | AW | ROB inlieu of LC No.108 between Nimbal-Indi road in Gadag -Hotgi section | Jan-19' |
8 | AW | RUB inlieu of LC No. 65 between Wandal-basavanabagewadi rioad in Gadag -Hotgi section | Mar/19 |
9 | AW | RUB in lieu of LC no.63 between Nittur -Sampige road stations in Tumakuru-Arisikere section. | Oct/18 |
10 | AW | RUB in lieu of LC no.71 between Banasandra- Kardi stations in Tumakuru-Arisikere section | Feb-19' |
11 | AW | RUB in lieu of LC no.80 between Kardi-Tiptur in Tumakuru-Arisikere- section. | August-18 |
12 | AW | RUB in lieu of LC no.91 between Honnavalli road-Adihalli in Tumakuru-Arisikere section. | Jun/18 |
13 | AW | RUB in lieu of LC no.92 between Honnavalli road-Adihalli in Tumakuru-Arisikere section. | May/18 |
14 | AW | RUB inlieu of LC No.181 between Sasalu-Mayakonda stations in Chickjajur-Hubballi section | Dec-18' |
15 | AW | RUB inlieu of LC No.187 between Kodaganur-Tolahunse stations in Chickjajur-Hubballi section. | Oct/18 |
16 | AW | RUB in lieu of LC No.245 between Karajgi- Savanur stations in Chickjajur-Hubballi section | Feb-19' |
17 | AW | RUB in lieu of LC No.250 between Karajgi- Savanur stations in Chickjajur-Hubballi section | Sep/18 |
18 | AW | RUB in lieu of LC No.252 between Karajgi- Savanur stations in Chickjajur-Hubballi section | Sep/18 |
19 | AW | RUB in lieu of LC No.255 between Savanur-Yelvigi stations in Chickjajur-Hubballi section | Jan-19' |
20 | AW | RUB in lieu of LC No.256 between Savanur-Yelvigi stations in Chickjajur-Hubballi section | Sep/18 |
21 | AW | RUB in lieu of LC No. 64 between Nimbal-Basavanabagewadi road stations in Gadag-Hotgi section. | Jan-19' |
22 | AW | RUB in lieu of LC No.101 -A between minchnal-Nimbal stations in Gadag-Hotgi section. | Jan-19' |
23 | AW | RUB in lieu of LC No.99 between pandavapura-srirangapatna stations in Ramanagaram-Mysuru section | Jan-19' |
24 | CS | - ROB in lieu of LC No.46 between Dharmapuri - Palakkodu stations in Salem-Yesvantpur section | Jun/18 |
25 | CS | - ROB in lieu of LC No.43 between Dharmapuri - Palakkodu stations in Salem-Yesvantpur section | 16 th JULY-18 |
26 | CS | -ROB in lieu of LC No.98 between Mulanur- Kuppam stations in Bengaluru-Jolarpet section | Dec-18' |
2019-20 |
1 | CS | - ROB in lieu of LC no:80 near Ibrahimpur with subway between Jumnal-Vijayapura stations in Gadag- Hotgi section | Feb-2020' |
2 | CS | ROB in lieu of LC No. 438 (Near Raybag) Raybag-Chinchli stations in Londa-Miraj section. | Feb-2020' |
3 | AW | RUB inlieu of LC No.234 between Byadgi-Haveri stations in Chickjajur-Hubballi section | April-2019' |
4 | AW | RUB inlieu of LC No.236 between Byadgi-Haveri stations in Chickjajur-Hubballi section | April-2019' |
5 | AW | RUB inlieu of LC No.241 between Haveri-Karajgi stations in Chickjajur-Hubballi section. | April-2019' |
6 | AW | RUB inlieu of LC No.254 between Savanur-Karajgi stations in Chickjajur-Hubballi section. | May-2019. |
7 | AW | RUB inlieu of LC No.219 between Ranebennuru-devaragudda stations in Chickjajur-Hubballi section. | Dec-19' |
8 | AW | RUB in lieu of LCNo. 51 between Devarapalle-Hindupur stations in Baiyyappanahalli-Dharmavaram section. | July-19' |
2020-21 |
1 | AW | Hubballi-Chickjajur - Doubling RUB inlieu of LC No.260 ( At Yelvigi Yard ) Savanur-Yelvigi | May/20 |
2 | AW | Hubballi-Chickjajur- Doubling. ROB in lieu of LCNo. 208 (In Harihar Yard)- 4 lanes | June-20' |
3 | AW | Hubballi-Chickjajur - Doubling RUB inlieu of LC No.283 ( At Hubballi south Yard ) | August-20' |
4 | AW | Bengaluru- Mysuru Doubling ROB inlieu of LC No. 68 ( At Hanakere Yard ) | August-20' |
5 | AW | Yelahanka-Penukonda Doubling. RUB in lieu of LCNo. 34 ( At Oddarahalli yard ) | May/20 |
6 | CS | JTJ -SBC section - LHS in lieu of LC no.136-A at Baiyyappanahalli at km 345/800-900. | Feb-21' |
7 | AW | Yelahanka-Penukonda Doubling. ROB in lieu of LCNo. 81 ( At Penukonda yard ) | June-20' |
8 | CS | BYPL-DMM section - RUB in lieu of LC no.9 at hegde Nagar at km 9/300-400 between YNK-CSDR stations | March-21' |