PROGRESS OF WORKS FOR THE MONTH OF
APRIL 2023
Cate-gory | Details of Work | Year of sanction | | Cum. Exp. Up to March 2023 | BG 2023-24 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-6 | Rayadurga-Tumkur(207Km)(12 Block sections) | 2007-08 | 2404.03 on 50:50 cost sharing basis between Rly and Gok / GoAP | 1098.72 | 225 Cr (Cap.&SF)
125 Cr(Dep.) | 42.5/ 1141.22 | 58% |
Remarks:- Section from Rayadurga-Kalyanadurga-Kadiridevarapalli (63 km) which falls in A.P. was commissioned in 2016-17.
Section between Kadiridevarapalli - Doddahalli (20 km) is has been commissioned on 15.02.2023.
The work for the remaining sections is planned to be taken up under Engineering Procurement & Construction mode of tendering after handing over of 90 % of land by Government of Karnataka. |