PROGRESS OF WORKS FOR THE MONTH OF
July 2020
Cate-gory | Details of Work | Year of sanction | | Cum. Exp. Up to March 2020 | RG 2020-21 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NLPB-6 | Rayadurga-Tumkur(207Km)(12 Block sections) | 2007-08 | 2062.30 on 50:50 cost sharing basis between Rly and Gok / GoAP | 984.81 | 59.99 | 74.68/ 1059.49 | 25% |
Remarks:- Section from Rayadurga-Kalyanadurga-Kadiridevarapalli (63 km) which falls in A.P. was commissioned in 2016-17. Work is in progress for a length of 12 km (Kadaridevarapalli-Kambadur) in A.P. For the land in balance length of 18 km in A.P. (MadakasiraTq), final notification under section 19(1) and award of compensation as per New L.A.Act has been issued by Govt. of A.P. for 158 Acres out of 206 Acres.Handing over land to be expedited.The work could not start in Karnataka State due to non-handing over of land in continuous length by GoK
i)Karnataka - As against the total requirement of 1396.26 acres (Tumkuru District), 614.91 acres has been handed over.
ii) Andhra Pradesh – As against the total requirement of 1023.00 acres (Anantpur district), 930.00 acres has been handed over. |