PROGRESS OF WORKS FOR THE MONTH OF
APRIL 2023
Cate-gory | Details of Work | Year of sanc-tion | Anticipated /Sanctioned Cost | Cum. Exp. Up to March 2023 | BG for 2023-24 | Exp. Up to the month/ Cum. Exp. | Physical progress |
NL PB-2 | Kadur-Chikmagalur-Sakleshpur (93kms) | 1996-97 | 826.18/534.88 On 50:50 cost sharing basis to Kadur-Chikmagalur (46km) & Chikmagalur – Sakleshpur (47 km) land free of cost and balance cost on 50:50 basis between Gok & Rly. | 499.19 | 85.00 (Cap. &SF) 60.00 (Likely Deposit)
| 0.018 /499.108
| 61% |
Remarks:-
Section from Kadur to Chikmagalur (46 km) was completed and commissioned on 19.11.2013.
Works between Chikmagalur – Sakleshpur were frozen by Railway Board since 2007 and defreezed during 2013. However, GoK vide G.O. No.IDD 95 NSW 2018 dated 17.01.2019 has advised that the section between Belur - Sakleshpur line stretch in Chikmagalur – Belur - Sakleshpura railway line to be dropped and to take up Belur-Hassan new railway line for which separate sanction from Railway Board dated 01.03.2019 has been received.
Railway Board vide letter dated 07.06.19 conveyed approval to freeze works on Belur-Sakleshpur in view of sanction of Hassan (Alur) - Belur NL project. Accordingly, work is taken up in Chikmagalur - Belur (22 km) section only.
Chikmagalur - Belur (22 km) - Planned to be executed in two phases:
- Chikmagalur - Hadihalli (9 km) - Engineering Procurement & Construction (EPC) Tender awarded on 09.02.2023 for a value of Rs. 121.39 Cr and is targeted to be commissioned by March 2024.
2. Hadihalli - Belur (13 km) - Proposed to be executed through Engineering Procurement & Construction (EPC) mode of tendering after handing over of 90% of the land by Government of Karnataka.