Kadur-Chickmagalur-Sakleshpur

PROGRESS OF WORKS FOR THE MONTH OF
APRIL 2023


Cate-gory

Details of Work

Year of sanc-tion

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2023

BG for 2023-24

Exp. Up to the month/ Cum. Exp.

Physical progress

NL

PB-2

Kadur-Chikmagalur-Sakleshpur

(93kms)

1996-97

826.18/534.88

On 50:50 cost sharing basis to Kadur-Chikmagalur (46km) & Chikmagalur – Sakleshpur (47 km) land free of cost and balance cost on 50:50 basis between Gok & Rly.

499.19

85.00 (Cap. &SF)

60.00 (Likely Deposit)


0.018 /499.108


61%

Remarks:-

Section from Kadur to Chikmagalur (46 km) was completed and commissioned on 19.11.2013.

Works between Chikmagalur – Sakleshpur were frozen by Railway Board since 2007 and defreezed during 2013. However, GoK vide G.O. No.IDD 95 NSW 2018 dated 17.01.2019 has advised that the section between Belur - Sakleshpur line stretch in Chikmagalur – Belur - Sakleshpura railway line to be dropped and to take up Belur-Hassan new railway line for which separate sanction from Railway Board dated 01.03.2019 has been received.   

       

Railway Board vide letter dated 07.06.19 conveyed approval to freeze works on Belur-Sakleshpur in view of sanction of Hassan (Alur) - Belur NL project. Accordingly, work is taken up in Chikmagalur - Belur (22 km) section only.

Chikmagalur - Belur (22 km) - Planned to be executed in two phases:

  1. Chikmagalur - Hadihalli (9 km) - Engineering Procurement & Construction (EPC) Tender awarded on 09.02.2023 for a value of Rs. 121.39 Cr and is targeted to be commissioned by March 2024.

2. Hadihalli - Belur (13 km) - Proposed to be executed through Engineering Procurement & Construction (EPC) mode of tendering after handing over of 90% of the land by Government of Karnataka.





Source : South Western Railway CMS Team Last Reviewed : 18-05-2023  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.